Machine Studies

Draft Schedule for Run01-8, 2018

March 19th 0800 – March 20th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 19, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1000

Reboot interleaving DSPs

OPS

Stored Beam & Injection

0930-1130

Reboot BSP100 iocs

Pietryla

No Beam

0930-1030

Replace intermittent flow detector at RF5

RF Group

No Injection

0930-1030

Reboot iocparbpm to test EPICS upgrade

Fors

Limited Injection

0930-1130

Swap quad converters

Ackley/Vargas

No Beam

1130-1200

Recovery and store beam

OPS

Stored beam & injection

1200-1300

Check response of rebooting the SCU IOCs in sectors 1 & 6

M. Smith

Stored beam & occ. injection

1300-1400

test new P0 feedback sample pattern scan script. Need injection to single bunch and 24 singlets

Yao, Shang

Stored beam & injection

1400-1800

Response matrix studies

Yipeng Sun

Stored beam & injection

1800-2200

Commissioning script development

Sajaev

Stored beam & injection

2200-2400

6 GeV studies

Emery

Stored beam & injection


Tuesday, March 20, 2018



0000-0200

6 GeV studies

Emery

Stored beam & injection

0200-0530

OPEN



0530-0700

Reboot of soft ioc used in HSCU control to test changes in software

M. Smith

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection