Machine Studies
Draft Schedule for Run01-8, 2018
March 19th 0800 – March 20th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 19, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving DSPs |
OPS |
Stored Beam & Injection |
0930-1130 |
Reboot BSP100 iocs |
Pietryla |
No Beam |
0930-1030 |
Replace intermittent flow detector at RF5 |
RF Group |
No Injection |
0930-1030 |
Reboot iocparbpm to test EPICS upgrade |
Fors |
Limited Injection |
0930-1130 |
Swap quad converters |
Ackley/Vargas |
No Beam |
1130-1200 |
Recovery and store beam |
OPS |
Stored beam & injection |
1200-1300 |
Check response of rebooting the SCU IOCs in sectors 1 & 6 |
M. Smith |
Stored beam & occ. injection |
1300-1400 |
test new P0 feedback sample pattern scan script. Need injection to single bunch and 24 singlets |
Yao, Shang |
Stored beam & injection |
1400-1800 |
Response matrix studies |
Yipeng Sun |
Stored beam & injection |
1800-2200 |
Commissioning script development |
Sajaev |
Stored beam & injection |
2200-2400 |
6 GeV studies |
Emery |
Stored beam & injection |
|
Tuesday, March 20, 2018 |
|
|
0000-0200 |
6 GeV studies |
Emery |
Stored beam & injection |
0200-0530 |
OPEN |
|
|
0530-0700 |
Reboot of soft ioc used in HSCU control to test changes in software |
M. Smith |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |