Draft Schedule for Run01-9, 2018

March 26th 0800 – March 27th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 26, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

Upgrade iocbbpm

Pietryla

Limited Injection

0930-1130

Swap quad converters

Ackley/Vargas

No Beam

0930-1130

Repair failed dump resistor T2 S38:39

Jordan

No Beam

0930-1130

measure real time feedback DSP processing delay.

S. Xu

No Beam

1130-1200

Recover SR

OPS

Stored beam & injection

1200-1300

continue test the P0 feedback sample pattern scan application. Need single and 24-singlet fill

Yao, Shang

Stored beam & injection

1300-1400

measure PAR dispersion. Need to adjust SR rf frequency

Yao

No beam

1400-2000

MOMBO and GAP scans

Sereno, Hahne

Stored beam & injection

2000-2400

Orbit switch

Xiao

Stored beam & injection


Tuesday, March 27, 2018



0000-0300

BPM sum signal calibration

Xiao

Stored beam & injection

0300-0700

Commissioning script development

Sajaev

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection