Machine Studies

Draft Schedule for Run02-1, 2018

May 22nd 0800 – May 30th 0800

Time

Descriptions

Studiers

SR Status


Tuesday, May 22, 2018



0800-1200

RF conditioning with beam

OPS

Stored Beam & Injection

0800-1200

BPM RTFB and datapool system checkout

Sereno

Stored Beam & Injection

1200-1600

BPLD validations

Lester/Sereno

Stored Beam & Injection

1600-2000

X-ray BPM sanity check

Sereno

Stored Beam & Injection

2000-2400

Lattice set up

Sajaev

Stored Beam & Injection


Wednesday, May 23, 2018



0000-0100

Lattice set up

Sajaev

Stored Beam & Injection

0100-0600

Orbit recovery

Xiao

Stored Beam & Injection

0600-0800

Open



0800-1400

Unified orbit feedback (parasitic) CANCELLED

Sereno et al

Stored beam

1030-1400

Changes to PEMs used to move gaps

Shang/Schroeder

Stored beam

0800-1400

Linac/PAR/Booster at 450 MeV

Sun/Pasky/Yao/Harkay/Calvey

No Injection

1400-1800

6 ID GRID XBPM commissioning

Yang

Stored Beam & Injection

1800-2400

Unified orbit feedback

Sereno, et al

Stored Beam


Thursday, May 24, 2018



0000-0400

Unified orbit feedback

Sereno, et al

Stored Beam

0400-0800

Commissioning script work

Sajaev

Stored Beam & Injection

0800-0900

Validate LINAC BESOCM

Keane

Limited Injection

0800-1100

Measure RTFB DSP processing delay

Xu, Paskvan

No beam

0900-1100

Validate Interleaving Trigger Control Chassis

Pietryla

Limited Injection

0830-1100

Check the cabling for the flow meter interlock on Sector 37 hybrid load 3

Goel

No Beam

1000-1100

RF waveguide switch

RF Group

No Beam

1100-1500

Linac waveguide switch testing and RG1 checkout

Sun

No Beam

1500-2100

450 MeV injector optimization

Yao, Harkay, Sun, Calvey

Stored Beam & Injection

2100-2400

Comissioning script work

Sajaev

Stored Beam & injection


Friday, May 25, 2018



0000-0700

Commissioning script work (cont.)

Sajaev

Stored Beam & Injection

0700

Fill SR with 324 singlets to 102mA for HP survey to be done in the afternoon

OPS

Stored Beam & Injection

0700-1300

PAR high charge study in 450MeV

Harkay/Calvey/Berenc

No injection

1300-1600

Return 425MeV injector

Sun/Pasky/Yao/Harkay

No injection

1600-1800

PEM testing with beam

Schroeder/Shang

Stored Beam & Injection

1800-2400

IEX checkout

Xiao

Stored Beam & Injection


Saturday, May 26, 2018



0000-0200

IEX checkout

Xiao

Stored Beam & Injection

0200-0900

Open



0900-1600

PAR high charge studie in 450MeV

Harkay/Calvey/Berenc

No injection

1600-2200

CPU checkout

Xiao

Stored Beam & Injection

2200-2400

Topup validation

OPS

Stored Beam & Injection


Sunday, May 27, 2018



0000-0800

Topup validation

OPS

Stored Beam & Injection

0800-1600

27-ID XBPM2, and 6-ID XBPM1 commissioning 24 singlets top-up(shutter permit needed)

Yang

Stored beam & injection

1600-2200

BTS study

Xiao

Stored Beam & Injection

2200-2400

Topup validation

OPS

Stored Beam & Injection


Monday, May 28, 2018



0000-0900

Topup validation

OPS

Stored Beam & Injection

0900-1600

Triple RHB lattice study

Sun

Stored Beam & Injection

1600-1900

ID4 aperture checkout

Emery

Stored Beam & Injection

1900-2400

6 GeV checkout

Emery

Stored Beam & Injection


Tuesday, May 29, 2018



0000

Fill 324 singlets for Yang's study at 0200

OPS

Stored beam & injection

0000-0800

450MeV High Charge study

Harkay

Limited injection

0200-0800

6-ID GRID-XBPM Calibration

Yang

Stored beam

0800-1200

Pinhole camera and bunch purity setup

Yang

Stored Beam & Injection

1200-1600

Final lattice setup

Sajaev

Stored Beam & Injection

1600-2000

Booster tune study with Lee Teng intern

Calvey

Limited injection

2000-2400

Final orbit setup

Xiao

Stored Beam & Injection


Wednesday, May 30, 2018



0000-0200

Abort kicker checkout

Harkay

Stored Beam & Injection

0200-0600

PAR RF System Manager file set-up

Harkay

Limited injection

0600-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection