Machine Studies

Draft Schedule for Run02-10, 2018

July 30th 0800 - July 31th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 30, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1000

Update Linac database record

Pietryla

Stored Beam & Injection

0930-1030

RF waveguide switch to RF2

RF Group

No Beam

0930-1130

Take internal measurements of IK4

Abid

No Beam

0930-1130

SR Septum IS1 power supply testing

Deriy

No Beam

0930-1130

Install new SR Quad control PS in Zone A

Vargas

No Beam

1000-1100

Test PAR rf pem

Harkay/ Soliday

No Beam

0930-1130

Upgrade iocbbpm3

Pietryla

No Injection

0930-1330

Validate 1-30Hz besocm

Keane

No Injection

1330-1430

Adjusting PAR fundamental rf and test SR injection

Harkay/Smith

Stored Beam & Injection

1430-1830

S27 FBC closed loop RM measurement and orbit feedback model benchmarking

Sereno et al.

Stored Beam & Injection

1830-2130

Booster tune studies

Calvey/Xu

Occasional Injection

1830-2030

Test TFB updated system

Yao/Shang/ Dimonte

Occasional Injection

2130-2400

27-ID XBPM2 calibration experiment

Yang

Stored Beam & Injection


Tuesday, July 31, 2018



0000-0300

27-ID XBPM2 calibration experiment

Yang

Stored Beam & Injection

0300-0700

RHB in ID25

Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection