Machine Studies
Draft Schedule for Run02-4, 2018
June 18th 0800 - June 19th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 18, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Replace external 24V PS for S9/10 vac MPS |
Benes |
No Beam |
0930-1130 |
Replace relays for S2/3 & S26/27 T2 energy dumping resistors |
PS Group |
No Beam |
0930-1130 |
RTFB DSP processing measurements |
Xu |
No Beam |
1000-1100 |
Map PAR bypass line for LTL removal |
Hoyt, Survey |
Access PAR |
1000-1100 |
Mount unistrut for PAR BLM cable |
Dombrowski |
Access PAR |
1100-1300 |
PAR chromaticity measurements and adjustment |
Yao/Harkay/Shang |
No Injection |
1300-1600 |
ID1 SCU perturbation |
Emery/Sarvjit |
Stored Beam & Injection |
1600-1700 |
XBPM sanity check script testing |
Hahne/Shang |
Stored Beam & Injection |
1700-1800 |
Libera Brilliance+ DDC mode noise study in S27 |
Sereno/Brill |
Stored Beam & Injection |
1800-2200 |
Sector 27 FBC closed loop response matrix measurements |
Sereno et al. |
Stored Beam & Injection |
2200-2400 |
6ID:P2 and 27ID:P2 testing (S27 shutter permit required) |
Sereno/Wootton/Bingxin |
Stored Beam & Injection |
|
Tuesday, June 19, 2018 |
|
|
0000-0200 |
6ID:P2 and 27ID:P2 testing (S27 shutter permit required) |
Sereno/Wootton/Bingxin |
Stored Beam & Injection |
0200-0700 |
Commissioning tool testing |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |