Machine Studies

Draft Schedule for Run02-9, 2018

July 23th 0800 - July 24th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 23, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

Troubleshoot PAR VTR1012 digitizer

DiMonte

No Injection

0930-1130

Measure SR IK4

Abid

No Beam

0930-1130

SR IS1 PS testing

Deriy

No Beam

0930-1130

Install 1-30Hz besocm

Keane

No Injection

1130-1330

Measure PAR kicker waveform with screen

Yao/Hillman

No Injection

1330-1500

SR Injection checkout (related to PAR rf phase issue)

Harkay/Yao/ Dimonte

Stored Beam & Injection

1500-1800

Test P0 feedback upgrade

Yao/Shang/ Dimonte

Stored Beam & Injection

1800-2200

Orbit Switch

Xiao

Stored Beam & Injection

2200-2400

RHB at ID25

Emery

Stored Beam & Injection


Tuesday, July 24, 2018



0000-0100

RHB at ID25

Emery

Stored Beam & Injection

0100-0400

Commissioning simulation

Sajaev

Stored Beam & Injection

0400-0700

Turn-by-Turn benchmarking

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection