Draft Schedule for Run03-1, 2018
September 25 0800 – October 2 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, September 24, 2018 Pre-Studies |
|
|
0900-1200 |
Set-up for RF conditioning with beam |
Schroedr/Flood/OPS |
Stored beam & injection |
1200-2400 |
RF conditioning with beam |
OPS |
Stored beam & injection |
1500-1900 |
BPM RTFB and datapool check-out (I>50mA) |
Sereno |
Stored beam & injection |
1500-1700 |
Initial pinhole camera set-up |
Yang |
Stored beam & injection |
|
Tuesday, September 25, 2018 |
|
|
0000-1200 |
RF Conditioning with beam (cont) |
OPS |
Stored beam & injection |
0800-1200 |
BPM RTFB and datapool check-out (I>50mA) -- (Continued is needed) |
Sereno |
Stored beam & injection |
1200-1600 |
BPLD validations |
Hahne/Sereno |
Stored beam & injection |
1600-2000 |
X-ray BPM check-out |
Hahne |
Stored beam & injection |
2000-2400 |
Initial lattice set-up |
Sajaev, Xiao |
Stored beam & injection |
|
Wednesday, September 26, 2018 |
|
|
0000-0500 |
BPM offset measurement (S29) & Orbit recovery |
Xiao |
Stored beam & injection |
0500-0900 |
Injector PEM testing |
Fystro |
Limited injection |
0900-1200 |
APD and bunch purity optimization setup |
Harkay, Yang, Yao |
Stored beam & injection |
1200-1600 |
Booster momentum offset variation studies (frequency changes -- no SR beam) |
Harkay, Yao |
No SR beam |
1600-2100 |
Injector kicker optimization |
Yipeng Sun |
Stored beam & injection |
2100-2400 |
Injection optimization |
Sajaev |
Stored beam & injection |
|
Thursday, September 27, 2018 |
|
|
0000-0100 |
Injection optimization (continued) |
Sajaev |
Stored beam & injection |
0100-0800 |
IEX checkout |
Xiao |
Stored beam |
0800-0900 |
RF waveguide switch and make adjustments to RF4 |
RF Group |
No Beam |
0800-1130 |
Update QPC Controller software |
Zientek |
No injection |
0800-1130 |
Troubleshoot L4 modulator PLC |
Meyer |
No injection |
0830-1130 |
Laser alignment |
Dooling |
Access Linac |
0830-1130 |
investigate SR power supply Interlock rack (old acis) drawings/wiring |
Puttkammer |
No beam |
0830-1130 |
End to end tests |
Belcher |
SR in CA |
0900-0930 |
Prepare for SR access -- Zone D |
OPS |
No Beam |
0930-1030 |
Re-route XBPM Grid signals at S27ID Current to Voltage conversion chassis |
Blake, Dombrowski |
Access Zone D |
1130-1230 |
Recovery SR & injectors |
OPS |
Stored beam & injection |
1230-1630 |
Commissioning TFB system. Need single bunch and 24 singlet fill |
Yao, DiMonte, Shang |
Stored beam & injection |
1630-1830 |
complete PAR kicker waveform scan with beam |
Yao |
Stored beam & injection |
1830-2300 |
Triple RHB lattice |
Emery, Yipeng Sun |
Stored beam & injection |
2300-2400 |
6GeV setup |
Emery |
Stored beam & injection |
|
Friday, September 28, 2018 |
|
|
0000-0300 |
6GeV setup (continued) |
Emery |
Stored beam & injection |
0300-0800 |
Injection optimization and P0 feedback setup |
Sajaev |
Stored beam & injection |
0800 |
Fill SR 24 singlets, OC and RTFB running |
OPS |
Stored beam & injection |
0830-0900 |
Test effect of vibratory plate ompactor with beam |
Flood, Russell |
Stored beam |
0830-1030 |
Troubleshoot PAR Harmonic #2 circuit breaker |
RF Group |
No injection |
0900-0930 |
Prepare for Zone D Access |
OPS |
No SR beam |
0915-1300 |
Update the ion pump controller software at 28 ID and 15 ID. gate valves will need to be closed |
Zientek |
No SR beam |
0930-1530 |
Remove photodiode assembly in S28 FE GRID X-bpm |
Oprondek, Hoyt |
Access Zone D |
1100-1300 |
Booster lattice/efficiency optimization |
Yao, Yipeng Sun |
No injection |
1300-1800 |
Booster momentum offset variation studies. Requires rf source frequency changes |
Harkay, Yao |
No SR beam |
1800-2400 |
CPU set-up |
Xiao |
Stored beam |
|
Saturday, September 29, 2018 |
|
|
0000-0900 |
Top-up verification |
OPS |
Stored beam & injection |
0900-1300 |
RG1 beam checkout |
Yine Sun |
Limited injection |
1300-1700 |
PAR digital camera commissioning |
Calvey, Yang, Wootton |
Limited injection |
1700-2400 |
Top-up verification |
OPS |
Stored beam & injection |
|
Sunday, September 30, 2018 |
|
|
0000-0900 |
Top-up verification |
OPS |
Stored beam & injection |
0900-1600 |
CPU/IEX set-up II if needed |
Xiao |
Stored beam |
1600-2200 |
28-ID GRID-XBPM initial study |
Yang |
Stored beam |
2200-2400 |
OPEN |
|
|
|
Monday, October 1, 2018 |
|
|
0000-0730 |
OPEN |
|
|
0730-0800 |
Prepare for Booster access |
OPS |
No injection |
0800-0930 |
Replace blower in inj. cav. #2 |
Wright |
Booster Access |
0900-0930 |
Prepare for SR Zone F access |
OPS |
No Stored Beam |
0930-1100 |
Replace Blower in S36 RF cavity |
Wright |
No Stored Beam |
1100-1200 |
Recover SR |
OPS |
Stored Beam & injection |
1200-1600 |
Final orbit set-up |
Xiao, Yipeng Sun |
Stored beam & injection |
1600-2000 |
Final lattice setup |
Sajaev |
Stored beam & injection |
2000-2100 |
Abort kicker set-up |
Harkay |
Stored beam & injection |
2100-2400 |
6ID GRID XBPM commissioning with controllaw |
Yang, Sereno |
Stored beam & injection |
|
Tuesday, October 2, 2018 |
|
|
0000-0100 |
6ID GRID XBPM commissioning with controllaw (continued) |
Yang, Sereno |
Stored beam & injection |
0100-0300 |
Final pinhole camera set-up/verifiy bunch purity |
Yang |
Stored beam & injection |
0300-0630 |
Commission script work |
Sajaev |
Stored beam & injection |
0630-0800 |
Prepare for user Operations (24 singlets – Top-Up) |
Ops |
Stored Beam & Injection |