Machine Studies
Draft Schedule for Run03-10, 2018
December 10th 0800 – December 11th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 10, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Investigate Booster RF tuner drive problem |
RF Group |
No Injection |
0930-1130 |
L5 SLED studies |
Smith |
Limited Injection |
0930-1130 |
Investigate BTS:BB breaker trips |
Vanis |
No Beam |
0930-1130 |
Swap quadrupoles Zone C |
Vargas |
No Beam |
1100-1400 |
Add monitoring to injector timing iocs for troubleshooting harmonic rf timing problem |
Yao, DiMonte, Fors |
1st 1/2 no PAR beam; no impact after |
1130-1200 |
Recover injectors/SR and fill |
OPS |
Stored beam & injection |
1200-1400 |
Linac training |
Weyer, Grodecki, Berg |
Limited Injection |
1200-1400 |
testing generating controllaw files and removing xray bpms from default configs |
Shang, Emery |
Stored beam |
1400-1500 |
Continue testing trajectory measurement script |
Shang, Sajaev |
Stored beam & injection |
1500-1900 |
LFB (324 singlets stored) |
Emery Kallakuri |
Stored beam |
1500-1700 |
Tuning booster injection and magnet ramps |
Calvey, Yao |
Occ. Inj. possible |
1700-1900 |
Linac training (15-23) |
Bogdan/Orne |
Limited Injection |
1900-2200 |
zBPM single bunch stored beam and single shot noise measuerements |
Sereno, Brill |
Stored beam & injection |
2200-2400 |
27-ID XBPM studies (shutter permit needed) |
Yang |
Stored beam & occ. inj. |
|
Tuesday, December 11, 2018 |
|
|
0000-0200 |
27-ID XBPM studies (shutter permit needed) -- continued |
Yang |
Stored beam & occ. inj. |
0200-0700 |
Commissioning script test |
Sajaev |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |