Machine Studies

Draft Schedule for Run03-2, 2018

October 9th 0800 – October 10th 0800



Time

Descriptions

Studiers

SR Status


Monday, October 8, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

Reboot iocs27vp. Change abort kicker pulse counter. Reboot iocs40bpm

Fors

No Beam

0930-1100

Finish up cabling in A014 for long. feedback system

Berenc

No Beam

0930-1030

Reboot FE iocs

Smith

Stored Beam & Injection

0930-1130

Swap SR quadrupole converters in Zone D

Vargas

No Beam

0930-1130

Swap out S11A:Q2 converter

Ackley

No Beam

0930-1130

Water header repair for 27AH3

Ackley

No Beam

0930-1130

Investigate RF-5 trips

Trento

No Injection

0930-1130

0-scope the scr flow meters

Trento

No Beam

1130-1200

Recover all systems -- store 24 singlets User orbit

OPS

Stored beam & injection

1200-1300

Move alignment stage for S27 GRID Xbpm

Yang, Sereno

Stored beam

1200-1400

upgrading iocbbpm3

Pietryla

Limited injection

1400-1800

check long. feedback system with new instrument

Emery, Wienand, Brill, Berenc

Stored beam & injection

1800-2200

Triple RHB lattice

Emery, Yipeng Sun

Stored beam & injection

2200-2300

PAR training (15-23)

Davis

Limited Injection

2300-2400

Linac klystron down-modes testing

Yine Sun

Limited injection


Tuesday, October 9, 2018



0000-0200

Linac klystron down modes testing (continued)

Yine Sun

Limited injection

0200-0500

OPEN



0500-0700

continue test of TFB system. Require store beam and injection occasionally

Yao

Stored beam & occ. injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection