Machine Studies
Draft Schedule for Run03-2, 2018
October 9th 0800 – October 10th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 8, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Reboot iocs27vp. Change abort kicker pulse counter. Reboot iocs40bpm |
Fors |
No Beam |
0930-1100 |
Finish up cabling in A014 for long. feedback system |
Berenc |
No Beam |
0930-1030 |
Reboot FE iocs |
Smith |
Stored Beam & Injection |
0930-1130 |
Swap SR quadrupole converters in Zone D |
Vargas |
No Beam |
0930-1130 |
Swap out S11A:Q2 converter |
Ackley |
No Beam |
0930-1130 |
Water header repair for 27AH3 |
Ackley |
No Beam |
0930-1130 |
Investigate RF-5 trips |
Trento |
No Injection |
0930-1130 |
0-scope the scr flow meters |
Trento |
No Beam |
1130-1200 |
Recover all systems -- store 24 singlets User orbit |
OPS |
Stored beam & injection |
1200-1300 |
Move alignment stage for S27 GRID Xbpm |
Yang, Sereno |
Stored beam |
1200-1400 |
upgrading iocbbpm3 |
Pietryla |
Limited injection |
1400-1800 |
check long. feedback system with new instrument |
Emery, Wienand, Brill, Berenc |
Stored beam & injection |
1800-2200 |
Triple RHB lattice |
Emery, Yipeng Sun |
Stored beam & injection |
2200-2300 |
PAR training (15-23) |
Davis |
Limited Injection |
2300-2400 |
Linac klystron down-modes testing |
Yine Sun |
Limited injection |
|
Tuesday, October 9, 2018 |
|
|
0000-0200 |
Linac klystron down modes testing (continued) |
Yine Sun |
Limited injection |
0200-0500 |
OPEN |
|
|
0500-0700 |
continue test of TFB system. Require store beam and injection occasionally |
Yao |
Stored beam & occ. injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |