Machine Studies
Draft Schedule for Run03-4, 2018
October 22nd 0800 – October 23rd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 22, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Waveguide switch to RF3/4 |
RF Group |
No Beam |
0930-10:00 |
Replace a vme fan tray on ioclirfgun |
Diviero |
No injection |
0930-1130 |
Linac recovery testing reboot iocs |
Fystro |
Limited Injection |
0930-1130 |
Investigate S37AV1 intermittently alarming minor |
Jordan |
No Beam |
0930-1130 |
Investigate S37AQ1 Latched fault for Mag Temp |
Jordan |
No Beam |
0930-1130 |
Investigate storage ring dipole intermittently alarming on GND fault |
Iftikhar, Puttkammer |
No Beam |
0930-1130 |
Reprogram temperature control points |
Erwin |
No Beam |
0930-1230 |
Test L5 for noise |
T. Smith |
Limited Injection |
1000-1100 |
Petra tour |
Volin/Vacca |
Access Zone A |
1000-1200 |
Identify noise source for S28 ID GRID XBPM (Shutting off PS in S29, possibly 28) |
Yang, Schroeder |
No Beam |
1030-1230 |
Test PAR RF-12 phase shifter |
Berenc |
Limited Injection |
1230-1330 |
Test PAR RF-12 phase shifter with beam |
Berenc |
Limited Injection |
1330-1530 |
continue test TFB system with beam. singlet or 24 singlet |
Yao, DiMonte |
Stored beam & injection |
1530-1800 |
upgrading iocbbpm3 |
Pietryla |
Limited injection |
1800-2300 |
Hybrid setup |
Xiao (Yao needed for P0 fdbk) |
Stored beam & injection |
2300-2400 |
Hybrid orbit recovery |
Xiao |
Stored beam & injection |
|
Tuesday, October 23, 2018 |
|
|
0000-0300 |
Hybrid orbit recovery |
Xiao |
Stored beam & injection |
0300-0700 |
Triple RHB |
Emery |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |