Machine Studies

Draft Schedule for Run01-1, 2019

January 22nd 0800 – January 29th 0800

Time

Descriptions

Studiers

SR Status


Tuesday, January 22, 2019



0000-1200

RF Conditioning with beam (cont)

OPS

Stored Beam & Injection

0800-1200

Initial pinhole camera set-up

Yang

Stored Beam & Injection

1200-1600

BPM RTFB and datapool check-out

Sereno

Stored Beam & Injection

1600-2000

BPLD validations

Hahne/Sereno

Stored Beam & Injection

2000-2400

X-ray BPM check-out

Hahne

Stored Beam & Injection


Wednesday, January 23, 2019



0000-0500

Initial lattice set-up

Sajaev/Xiao

Stored Beam & Injection

0500-1000

Orbit recovery

Yipeng Sun

Stored Beam & Injection

1000-1100

Restore and test PAR harmonic rf timing

DiMonte/Yao

Stored Beam & Injection

1100-1300

Test BTS dipole conditioning script

Harkay/Soliday

Limited injection

1300-1700

Test TFB feedback system

DiMonte/Yao

Stored Beam & Injection

1700-2400

LFB 324 fill, 115 mA

Emery/Wienands /Kallakuri

Stored Beam & Injection


Thursday, January 24, 2019



0000-0100

LFB 324 fill, 115 mA

Emery/Wienands /Kallakuri

Stored Beam & Injection

0100-0600

IEX/CPU perturbation collection, 324 fill (Xiao will give instruction)

OPS

Stored Beam & Injection

0600-1000

Test xBPM sanity check script, 324 fill

Hahne

Injection at the beginning

0800-0800

Test modifications to iocbbpm3

Pietryla

No Injection

0800-1000

Test switching for BSD-U and BSD

PS Group

No Injection

0800-1400

Checking for problem at SR Dipole magnets (if occurs will cancel waveguide switch below)

PS Group

Access SR (possibly all zones)

0800-1400

RF3 supplying Booster waveguide switch to RF3/RF4 (will occur if SR access cancelled)

RF Group

Limited injection/No Beam

0830-1130

Laser alignment

Dooling

Access Linac

1400-1800

Testing zBPM (moved to later because of RF5 problem)

Sereno/Brill

Stored Beam & Injection

1800-2000

Verify P0 feedback system after replacement of the clock source

Yao

Stored Beam & Injection

2000-2400

Tune PAR for high charge

Harkay/Calvey

No injection


Friday, January 25, 2019



0000-0200

Tune PAR for high charge

Harkay/Calvey

No injection

0200-0800

Testing zBPM

Sereno/Brill

Stored Beam & Injection

0800-1000

Setup SF-U operations

Yao

No injection

1000-1400

ID corrector feed-forward table check-out

Emery

Stored Beam & Injection

1400-1800

BTS FS3 YAG screen testing

Wootton/Lumpkin

Limited injection

1800-2200

Booster tuning

Calvey

No injection

2200-2400

Open




Saturday, January 26, 2019



0000-1000

Open



1000-1800

CPU/IEX check-out

Xiao

Stored Beam & Injection

1800-1900

Abort Kicker studies

Harkay

Stored beam & injection

1900-2200

BTS Dipole Conditioning studies

Harkay

Stored beam & injection

2200-2400

Top-up verification

OPS

Stored Beam & Injection


Sunday, January 27, 2019



0000-1000

Top-up verification

OPS

Stored Beam & Injection

1000-1800

6 GeV setup

Emery

Stored Beam & Injection

1800-2400

Commissioning script work

Sajaev

Stored Beam & Injection


Monday, January 28, 2019



0000-0600

Top-up verification

OPS

Stored Beam & Injection

0600-0800

Final pinhole camera set-up

Yang

Stored Beam & Injection

0800-1000

Bunch purity setup

Harkay

Stored Beam & Injection

1000-1400

Setup Booster extraction and BTS for 6 GeV, measure emittance

Yao/Calvey/Wootton/Lumpkin/Xiao

No Injection

1400-2000

Vary Booster momentum offset and measure beam (SLM,BDM) and emittance (BTS, BTX)

Yao/Calvey/Wootton/Dooling/Lumpkin/Xiao

No Injection

2000-2400

Final orbit set-up

Yipeng Sun

Stored Beam & Injection


Tuesday, January 29, 2019



0000-0630

Final lattice setup

Sajaev/Xiao

Stored Beam & Injection

0630-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection