Machine Studies

Draft Schedule for Run01-4, 2019

February 18th 0800 – February 19th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 18, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

Swap phase detector module in RF2 LLRF

Madden

No Beam

0930-1030

Switch over pumps 903, 401, 521 (bump-less)

Wright

No Beam

0930-1130

Install ZVV meters in Zone B T1

Vargas

No Beam

0930-1130

Check (replace)cable connections in BSF-U PS

Vanis

No Beam

0930-1130

Continue work on iocbbpm3

Pietryla

Limited Injection

0930-1130

Replace INJ cavity 2 tuner control crate

Yoder

No Beam

1000-1100

Check PAR RTD connections

Erwin

Access PAR

1130-1200

Recover SR

OPS

Stored Beam & Injection

1200-1600

XBPM MOMBO Gap scans

Sereno

Stored Beam & Injection

1600-1800

Investigate 11 BM X-BPM readback

Yang/Hahne

Stored Beam & Injection

1800-2100

Test transverse FB system

Yao/Dimonte

Stored Beam & Injection

2100-2400

BTS measurement

Xiao

Limited Injection


Tuesday, February 19, 2019



0000-0300

BTS measurement

Xiao

Limited Injection

0300-0700

BPM offset measurement

OPS

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection