Machine Studies
Draft Schedule for Run01-6, 2019
March 4th 0800 – March 5th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 4, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1130 |
Troubleshoot/test DAC boards in S12:13 |
Jordan |
No Beam |
0930-1130 |
Replace filters on P-SR-20 and P-SR-30 – no flow – SR dipole, PS in 18-21 and 28-31 off |
Swetin |
No Beam |
0930-1130 |
Testing SROrbitControllaw |
Shang |
No Beam |
0930-1130 |
Work on MCC for pump 525 |
Wright |
No Beam |
1000-1100 |
APSU ID inspection |
Smith/Grimmer |
Access Zone A |
0930-1130 |
PAR training (07-15) |
Orne/Bogdan |
Limited Injection |
1130-1200 |
Recover SR |
OPS |
Stored Beam & Injection |
1200-1500 |
XBPM mombo scan |
Hahne/Shang |
Stored Beam & Injection |
1500-1800 |
Test transverse feedback system |
Yao/Dimonte |
Stored Beam & Injection |
1800-2300 |
BTS dispersion measurement (changing rf frequency) |
Emery/Xiao |
No beam |
2300-0100 |
SR training (23-07) |
Davis/LaBuda |
Stored Beam & Injection |
|
Tuesday, March 5, 2019 |
|
|
0000-0100 |
SR training (23-07) |
Davis/LaBuda |
Stored Beam & Injection |
0100-0700 |
Commissioning tests |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |