Machine Studies

Draft Schedule for Run01-6, 2019

March 4th 0800 – March 5th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 4, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

Troubleshoot/test DAC boards in S12:13

Jordan

No Beam

0930-1130

Replace filters on P-SR-20 and P-SR-30 – no flow – SR dipole, PS in 18-21 and 28-31 off

Swetin

No Beam

0930-1130

Testing SROrbitControllaw

Shang

No Beam

0930-1130

Work on MCC for pump 525

Wright

No Beam

1000-1100

APSU ID inspection

Smith/Grimmer

Access Zone A

0930-1130

PAR training (07-15)

Orne/Bogdan

Limited Injection

1130-1200

Recover SR

OPS

Stored Beam & Injection

1200-1500

XBPM mombo scan

Hahne/Shang

Stored Beam & Injection

1500-1800

Test transverse feedback system

Yao/Dimonte

Stored Beam & Injection

1800-2300

BTS dispersion measurement (changing rf frequency)

Emery/Xiao

No beam

2300-0100

SR training (23-07)

Davis/LaBuda

Stored Beam & Injection


Tuesday, March 5, 2019



0000-0100

SR training (23-07)

Davis/LaBuda

Stored Beam & Injection

0100-0700

Commissioning tests

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection