Machine Studies

Draft Schedule for Run02-10, 2019

August 5th 0800 – August 6th 0800



Time

Descriptions

Studiers

SR Status


Monday, August 5, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

0930-1000

Place power meter in line with Libera processor

Blake

No Beam

0930-1000

PSS end to end test 6ID

McNamara

No Beam (SR dipole off)

0930-1130

replace water pump for the PC-GUN.30

Wright

No injection

0930-1100

Replace 5V PS in S30:31 interlock rack

Ackley

No Beam

0930-1130

Move temperature measurement equipment S14

Erwin

No Beam

0930-1300

Install noise suppression “Pre-amp Phase Shifter” chassis & may install a different 400W amp

T. Smith

No injection

1000-1200

SR bucket selection

Emery, Shoaf, Fors, Lenkzsus

No beam

1100-1300

Test sr feedback ioc software, may reboot feeback iocs (needs all P.S. on)

S. Xu

No beam

1300-1500

SR training (07-15)

Weyer/Davis

Stored Beam & Injection

1500-1800

Test TFB. Single bunch or hybrid fill

Yao

Stored Beam & injection

1800-2100

IEX beamline emittance measurement (324 singlets) (shutter permit needed)

Wootton, McChesney (29-ID)

Stored beam

1800-2400

BTS Measurements

Xiao

Occ. injection possible

2100-2400

6 GeV ID feedforward scan. < 100 mA. 324 bunches

Emery

Stored beam


Tuesday, August 6, 2019



0000-0530

HOM search. < 100 mA 648 bunches.

Emery Kallakuri

Stored beam & Injection

0530-0700

Injector training (23-07)

Grodecki/Berg

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection