Draft Schedule for Run02-11, 2019
August 12th 0800 – August 13th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, August 12, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
0930-1130 |
Move temperature measurement equipment S16 |
Diag |
No Beam |
0930-1300 |
L5 Pre-amp phase shifter modifications |
Smith |
Limited Injection |
1300-1400 |
Injector training (07-15) |
Weyer/Grodecki/Berg |
Stored Beam & Injection |
1400-1600 |
to combine and test switching P0FB and TFB systems. 24 singlet or single bunch. |
Yao |
Stored beam & injection |
1600-1700 |
observe kicker/septum noise on the LTP and PTB current monitors. Beam through the PAR required. |
Keane |
Limited injection |
1600-1800 |
test square matrix using sector 18 ID XBPMs (24 singlets) |
Sereno |
Stored Beam |
1800-2200 |
IEX beamline emittance measurement (shutter permit needed) (324 singlets) |
Wootton, McChesney (29-ID) |
Stored Beam |
1800-2000 |
PAR dipole conditioning studies and checkout with beam. |
Fystro, Harkay |
Limited injection |
2000-2200 |
BTS:BB setpoint optimization. Frequent injection needed. |
Fystro, Harkay, Emery |
Limited injection |
2200-2400 |
Triple RHB for S25. Optics correction |
Emery/Yipeng Sun/Sajaev |
Stored beam & injection |
|
Tuesday, August 13, 2019 |
|
|
0000-0200 |
Triple RHB for S25. Optics correction |
Emery/Yipeng Sun/Sajaev |
Stored beam & injection |
0200-0700 |
HOM Search |
Emery |
Stored beam & occ. injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |