Draft Schedule for Run02-2, 2019
June 3rd 0800 - June 4th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 3, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Access ITS |
Zholents |
No Injection L1-3 RF off and locked out |
0930-1130 |
Update databases and medm screens for L1-3 drive amplifiers |
Pietryla |
No Beam |
0930-1530 |
L5 conditioning |
RF Group |
Limited Injection |
0930-1730 |
RF-5 klystron instability troubleshooting |
RF Group |
No Injection |
1000-1100 |
Open and lock FE fast valve into position |
Clute |
Access Zone B |
1000-1100 |
Switch from backup to pump 902 -- will NOT be bumpless -- RF2 should be off to avoid trip -- |
Wright |
No injection |
1530-1730 |
PAR training (15-23) |
Bogdan/Orne |
Limited Injection |
1730-1930 |
test TFB application. Need injection to different fill patterns |
Yao, Shang, DiMonte |
Stored beam & injection |
1930-2130 |
Continue investigation of bunch purity (may push following studies later) |
Multiple |
Stored beam & injection |
2130-2400 |
look for weak HOMs at 7 GeV @ 115mA |
Emery/Wienands /Kallakuri |
Stored beam & injection |
|
Tuesday, June 4, 2019 |
|
|
0000-0330 |
Look for weak HOMs at 7 GeV @ 115mA (continued) |
Emery/Wienands /Kallakuri |
Stored beam & injection |
0330-0430 |
Bpm offset of S37B:P1 S38A:P1 in x plane |
Emery |
Stored beam & injection |
0430-0530 |
Repeat 6 GeV response matrix |
Emery |
Stored beam & injection |
0530-0630 |
Restore to 7GeV operations & verify |
Emery |
Stored beam & injection |
0630-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |