Draft Schedule for Run02-3, 2019
June 10th 0800 - June 11th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 10, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1130 |
Investigate PAR dipole PS CT |
Vanis |
No Injection |
0930-1130 |
Swap Zone B converters |
Vargas |
No Beam |
0930-1130 |
Modify Linac timing databases |
Pietryla |
No Injection/ LRF off |
1000-1100 |
Replace S37 Cavity blower |
MOM |
Access Zone F |
1000-1100 |
Install some waveguide at the output of the test stand load circulator |
RF Group |
No impact |
1000-1130 |
Install fast monitor in PAR |
Dooling |
Access PAR |
1130-1200 |
Store beam -324 singlets |
OPS |
Stored beam & injection |
1200-1400 |
Test dispersion correction for bpm setpoints. Gaps to close |
Emery, Shang |
Stored beam |
1200-1600 |
L5 conditioning/verify L5 VSWR levels |
RF Group |
Limited injection |
1400-1600 |
Linac tune-up (parasitic to L5 conditioning) |
Yine Sun |
Limited injection |
1600-1800 |
test SR bunch cleaning |
Yao, Keane |
Stored beam & inj. |
1800-2130 |
bunch purity investigation |
Harkay |
Stored beam & inj. |
2130-2300 |
SR training (15-23) |
LaBuda/Davis |
Stored Beam & Injection |
2300 -2400 |
IEX perturbation study. |
Xiao |
Stored beam |
|
Tuesday, June 11, 2019 |
|
|
0000-0300 |
IEX perturbation study(continued) |
Xiao |
Stored beam |
0000-0200 |
Injector training (23-07) |
Bogdan/Orne |
Limited Injection |
0300-0700 |
Commissioning tests |
Sajaev |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |