Draft Schedule for Run02-4, 2019

June 17th 0800 - June 18th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 17, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0900-0930

Intentional dumps with gaps closed, then gaps open to evaluate S38 cavity response

OPS

Stored Beam & Injection

0930-1130

Pump switch overs 401, 503, 513, 515, 521, 533

Wright

No Beam, PS at zero

0930-1130

Investigate SR IK3 DAC clamp

Abid

No Injection

0930-1130

Swap Zone B converters

Vargas

No Beam

0930-1130

Measure TFB amplifier response

Yao

Limited Injection

0930-1130

Install keysight multimeter in iocpar02

Pietryla

Limited Injection

0930-1130

Evaluate PAR kicker noise on the LTP and PTB current monitors

Keane

Limited injection

0930-1130

L5 conditioning

RF Group

Limited injection

0930-1030

Reconfigure analog output of S38 RF Cavity cold cathode gauges

MOM/RF

No beam

1030-1130

Tests to determine the S38 RF cavity causing the faults resulting in beam losses

Emery/RF Group

No beam

1130-1230

Continue S38 RF cavity vacuum tests with beam

Emery/RF Group

Stored beam & injection

1230-1400

Possibly blank off one of S38 RF cavities

RF Group

No beam

1230-1400

PAR console testing

Fystro/Orne

Limited injection

1130-1330

Install/move network cables

Pietryla

Stored Beam & Injection

1530-1600

adjust linac L5 RF level and SLED timing

Yine Sun

Occasional injection possible

1600-1800

Bunch cleaning test. 24 singlet fill pattern

Yao

Stored beam & injection

1800-2200

Bunch purity studies

Harkay, Yang, Emery

Stored beam & injection

2200-2400

HOM search. 432 bunches

Emery, Kallakury

Stored beam


Tuesday, June 18, 2019



0000-0200

HOM search. 432 bunches (continued)

Emery, Kallakury

Stored beam

0200-0600

IEX perturbation measurements

Xiao

Stored Beam

0600-0700

SR training (23-07)

LaBuda/Davis

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection