Draft Schedule for Run02-5, 2019

June 24th 0800 - June 25th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 24, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1000

Switch back to primary pump in PAR. Not bumpless

Wright

No injection

0930-1030

Investigate L2:SC2:VL P.S.

Puttkammer

No injection

0930-1130

Test the vacuum fast fault chassis in S38 rf cavities

Bromberek

No Beam

0930-1030

Replace RF test stand keystroke window air blower

Wright

No Beam

0930-1000

Change MPS limit to 115mA

M. Smith

No Beam

0930-1130

Replace 5V control power supply in S8 & 11

Vargas/Ackley

No Beam

0930-1130

Move temperature monitoring system equipment

Erwin

No Beam

1000-1130

PAR training (07-15)

LaBuda/Orne

Stored Beam & Injection

1000-1030

Check cable connection for S38 cold cathode

Gagliano

Access Zone F

1100-1230

SR training (07-15)

LaBuda/Davis

Stored Beam & Injection

1230-1630

Induce beam dumps in S38 cavities.

Emery/RF Group

Stored Beam & injection

1630-1930

PAR loss factor measurement with SR scope

Yao

PAR beam only

1630-1730

single bunch beam in SR to check S9 and S17 bpm timing

Sereno

Stored beam

1730-1930

orbit correction Start button test -- no beam needed

Shang

Stored beam or no beam

1930-2330

Orbit switch

Yipeng Sun

Stored Beam & injection

2330-2400

Remeasure response matrix at 6 GeV

Emery

Stored Beam & injection


Tuesday, June 25, 2019



0000-0130

Remeasure response matrix at 6 GeV

Emery

Stored Beam & injection

0130-0630

commissioning tests

Sajaev

Stored Beam & injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection