Machine Studies

Draft Schedule for Run02-6, 2019

July 3rd 0800 – July 5th 0800



Time

Descriptions

Studiers

SR Status


Wednesday, July 3, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne/Sereno

Stored Beam & Injection

0930-1100

Injector training

LaBuda/Orne

Limited injection

0930-1030

Replace RF Test Stand keystroke window blower

Wright

No Beam

0930-1030

Switch pumps 401,503,513,515,521,and 533 back to lead pump. Bump less switch PS set to zero (S4 through 7, S14 through 19, S22 through 25, S34 through 1)

Wright

No Beam

1000-1100

Troubleshoot 20-BM shutter

Gagliano

Access Zone C

1000-1100

Troubleshoot S33-34 control valve operation

Putnam

No Beam

1100-1300

SR training (07-15)

LaBuda/Davis

Stored Beam & Injection

1300-1500

investigate S9B and S17B bpm TBT relative delay at injection.

Sereno

Stored beam & inj.

1500-2100

Bunch purity studies

Harkay, Yang

Stored beam & Inj.

2100-2400

OPEN




Thursday, July 4, 2019



0000-0200

Injector training (23-07)

Grodecki/Berg

Limited injection

0200-0600

OPEN



0600-1400

HOM search

Emery, Kallakuri

Stored beam & Inj.

1400-1800

Testing orbit correction "Start" button with SR beam

Shang

Stored beam

1800-2000

Injector training (15-23)

Bogdan/Orne

Stored Beam & Injection

2100-2400

PAR High Charge studies

Harkay

Limited inj.


Friday, July 5, 2019


00

0000-0200

PAR High Charge studies (continued)

Harkay

Limited inj.

0200-0400

Injector training (23-07)

Grodecki/Berg

Stored Beam & Injection

0400-0700

OPEN



0700-0800

Prepare for User beam

OPS

Stored Beam & Injection