Machine Studies
Draft Schedule for Run02-7, 2019
July 15th 0800 – July 17th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 15, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1700 |
Install LtL stop(PAR access) 9:00-14:00/ Recovery and Rad survey (Booster access) & Booster recovery 14:00-17:00 |
Hoyt, SI, MOM |
Access Par & booster |
0930-1030 |
RF waveguide switch from RF1 to RF4 |
RF Group |
No Beam |
0930-1030 |
Swap out S29B:H1 corrector P.S. |
Puttkammer |
No Beam |
0930-1130 |
Replace cabinet 5V control power supply |
Ackley/Jordan |
No Beam |
0930-1130 |
Troubleshoot RF5 1400V A-phase readback |
RF Group |
No Beam |
0930-1130 |
Replace RTD for RF-2 process water |
Putnam |
No Beam RF off |
0930-1130 |
Replace S33-34 control valve actuator |
Putnam |
No Beam |
0930-1130 |
Move temperature measurement system in S8 |
Erwin |
No Beam |
1015-1100 |
Troubleshoot 20-BM shutter |
Gagliano |
Access Zone C |
1100-1300 |
Test booster lattice switch pem 2 Hz to 1 Hz and back; measure SD-U, SF-U dI/I error. |
Yao, Calvey, Harkay |
No beam needed |
1115-1230 |
Replace S38 Cavity #2 Blower |
MOM |
Access Zone F |
1300-1500 |
test sr feedback ioc software, may reboot all feeback iocs (all SR P.S. need to be on) |
S. Xu |
No beam |
1500-1700 |
Software testing for ID gap feedforward for energy loss. |
Emery/Shang |
Beam not necessary |
1700-2100 |
tune SR to booster rf phase, fill 24 bunches to 80-100 mA, no topup and measure bunch purity, high resolution |
Harkay, Yang, Emery |
Stored beam & occ. injec. |
2100-2300 |
Set up injectors in 1 Hz for 2 nC and fill storage ring in 324- and 24-bunch fill patterns |
Harkay |
Stored beam & injection |
2300-2400 |
Injector training (23-07) |
Bogdan/Orne |
Stored Beam & Injection |
|
Tuesday, July 16, 2019 |
|
|
0000-0100 |
Injector training (23-07) |
Bogdan/Orne |
Stored Beam & Injection |
0100-0600 |
Set up hybrid |
Emery, Xiao, Sajaev |
Stored Beam & injection |
0600-1000 |
Orbit switch |
Yipeng Sun |
Stored Beam & Inj. |
1000-1300 |
beam-based orbit response measurements at S27/28 with long-duration corrector drive waveform |
Carwardine, Fors, Veseli |
Stored Beam & Inj. |
1300-1600 |
test SR bunch cleaning with TFB+VSA chirp |
Yao |
Stored Beam & inj. |
1600-1800 |
SR training (15-23) |
LaBuda/Davis |
Stored Beam & Injection |
1800-2400 |
HOM search |
Emery Kallakuri |
Stored beam & occ. inj. |
1800-2400 |
BTS measurement |
Xiao |
Occ inj. possible |
|
Wednesday, July 17, 2019 |
|
|
0000-0100 |
HOM search (continued) |
Emery Kallakuri |
Stored beam & occ. inj. |
0100-0630 |
Commissioning tests |
Sajaev |
Stored beam & inj. |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |