Machine Studies

Draft Schedule for Run02-7, 2019

July 15th 0800 – July 17th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 15, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1700

Install LtL stop(PAR access) 9:00-14:00/ Recovery and Rad survey (Booster access) & Booster recovery 14:00-17:00

Hoyt, SI, MOM

Access Par & booster

0930-1030

RF waveguide switch from RF1 to RF4

RF Group

No Beam

0930-1030

Swap out S29B:H1 corrector P.S.

Puttkammer

No Beam

0930-1130

Replace cabinet 5V control power supply

Ackley/Jordan

No Beam

0930-1130

Troubleshoot RF5 1400V A-phase readback

RF Group

No Beam

0930-1130

Replace RTD for RF-2 process water

Putnam

No Beam RF off

0930-1130

Replace S33-34 control valve actuator

Putnam

No Beam

0930-1130

Move temperature measurement system in S8

Erwin

No Beam

1015-1100

Troubleshoot 20-BM shutter

Gagliano

Access Zone C

1100-1300

Test booster lattice switch pem 2 Hz to 1 Hz and back; measure SD-U, SF-U dI/I error.

Yao, Calvey, Harkay

No beam needed

1115-1230

Replace S38 Cavity #2 Blower

MOM

Access Zone F

1300-1500

test sr feedback ioc software, may reboot all feeback iocs (all SR P.S. need to be on)

S. Xu

No beam

1500-1700

Software testing for ID gap feedforward for energy loss.

Emery/Shang

Beam not necessary

1700-2100

tune SR to booster rf phase, fill 24 bunches to 80-100 mA, no topup and measure bunch purity, high resolution

Harkay, Yang, Emery

Stored beam & occ. injec.

2100-2300

Set up injectors in 1 Hz for 2 nC and fill storage ring in 324- and 24-bunch fill patterns

Harkay

Stored beam & injection

2300-2400

Injector training (23-07)

Bogdan/Orne

Stored Beam & Injection


Tuesday, July 16, 2019



0000-0100

Injector training (23-07)

Bogdan/Orne

Stored Beam & Injection

0100-0600

Set up hybrid

Emery, Xiao, Sajaev

Stored Beam & injection

0600-1000

Orbit switch

Yipeng Sun

Stored Beam & Inj.

1000-1300

beam-based orbit response measurements at S27/28 with long-duration corrector drive waveform

Carwardine, Fors, Veseli

Stored Beam & Inj.

1300-1600

test SR bunch cleaning with TFB+VSA chirp

Yao

Stored Beam & inj.

1600-1800

SR training (15-23)

LaBuda/Davis

Stored Beam & Injection

1800-2400

HOM search

Emery Kallakuri

Stored beam & occ. inj.

1800-2400

BTS measurement

Xiao

Occ inj. possible


Wednesday, July 17, 2019



0000-0100

HOM search (continued)

Emery Kallakuri

Stored beam & occ. inj.

0100-0630

Commissioning tests

Sajaev

Stored beam & inj.

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection