Machine Studies
Draft Schedule for Run02-9, 2019
July 29th 0800 – July 30th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 29, 2019 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/Fystro |
Stored Beam & Injection |
0930-1030 |
BTS/SR PEM testing |
Fystro/Soliday |
No Beam |
0930-1030 |
Investigate L1:RG1:SC2:HZ status |
Donkers |
Limited Injection |
0930-1100 |
Replace solenoid valve S37 hybrid load #3 |
Swetin |
No Beam |
0930-1100 |
Investigte double injections |
Shoaf, Fors |
No Beam |
0930-1130 |
Move temperature measurement equipment S10 |
Erwin |
No Beam |
0930-1130 |
Determine optimal keystroke filament power for L4 & 5 |
RF Group |
No Injection |
1015-1100 |
Replace RF-5 cavity #4 blower |
MOM |
Access Booster |
1100-1300 |
RF-3 efficiency testing |
RF Group |
Stored Beam & Injection |
1300-1500 |
Set-up Injectors for 375 MeV |
OPS/Harkay |
Stored Beam & injection |
1500-1700 |
test run TFB system in hybrid mode. hybrid fill |
Yao |
Stored Beam & injection |
1700-2000 |
IEX beamline emittance measurement (shutter permit needed) |
Wootton/29-ID personnel |
Stored Beam & injection |
2000-2400 |
Orbit switch |
Yipeng Sun |
Stored beam & injection |
|
Tuesday, July 30, 2019 |
|
|
0000-0430 |
Commissioning tests |
Sajaev |
Stored beam & injection |
0430-0630 |
linac bunch length measurements |
Yine Sun, Borland |
No injection |
0630-0800 |
Prepare for User beam (24 singlets) |
OPS |
Stored Beam & Injection |