Machine Studies

Draft Schedule for Run02-9, 2019

July 29th 0800 – July 30th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 29, 2019



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/Fystro

Stored Beam & Injection

0930-1030

BTS/SR PEM testing

Fystro/Soliday

No Beam

0930-1030

Investigate L1:RG1:SC2:HZ status

Donkers

Limited Injection

0930-1100

Replace solenoid valve S37 hybrid load #3

Swetin

No Beam

0930-1100

Investigte double injections

Shoaf, Fors

No Beam

0930-1130

Move temperature measurement equipment S10

Erwin

No Beam

0930-1130

Determine optimal keystroke filament power for L4 & 5

RF Group

No Injection

1015-1100

Replace RF-5 cavity #4 blower

MOM

Access Booster

1100-1300

RF-3 efficiency testing

RF Group

Stored Beam & Injection

1300-1500

Set-up Injectors for 375 MeV

OPS/Harkay

Stored Beam & injection

1500-1700

test run TFB system in hybrid mode. hybrid fill

Yao

Stored Beam & injection

1700-2000

IEX beamline emittance measurement (shutter permit needed)

Wootton/29-ID personnel

Stored Beam & injection

2000-2400

Orbit switch

Yipeng Sun

Stored beam & injection


Tuesday, July 30, 2019



0000-0430

Commissioning tests

Sajaev

Stored beam & injection

0430-0630

linac bunch length measurements

Yine Sun, Borland

No injection

0630-0800

Prepare for User beam (24 singlets)

OPS

Stored Beam & Injection