Machine Studies
Schedule for Run03-1, 2019
September 24th 0800 – October 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, September 23, 2019 |
|
|
0800-1630 |
Downtime - SR Dipole P.S. |
|
|
1630-1845 |
Set up injection and check aperture of S25 BPM with 20 mA, includion |
Emery/OPS |
Stored beam & injection |
1845-2400 |
RF conditioning with beam |
OPS |
Stored beam & injection |
|
Tuesday, September 24, 2019 |
|
|
0000-1100 |
RF conditioning with beam (cont) Hold at 115 mA for 20 minutes |
OPS |
Stored beam & injection |
0000-0400 |
BPM RTFB and datapool check-out (parasitic to conditioning with beam |
Sereno |
Stored Beam & Injection |
1100-2400 |
Downtime -- Investigation of SR IS1 |
Multiple |
No SR Beam |
1600-1700 |
Measure LTP/PTB current monitor kicker noise with beam |
Keane |
No SR injection |
|
Wednesday, September 25, 2019 |
|
|
0000-2400 |
Downtime -- Investigation of SR IS1 |
Multiple |
No SR Beam |
1000-1500 |
Laser alignment |
Dooling |
Linac Access |
1230-1300 |
Replacement of an IR temperature sensor for sector 38 C3 |
McKenzie |
Zone F Access |
|
Thursday, September 26, 2019 |
|
|
0000-2400 |
Downtime -- Investigation/Replacement of SR IS1 |
Multiple |
No SR Beam |
0600-1400 |
Linac RF conditioning |
RF Group |
No injection |
1300:1600 |
425 MeV setup |
Yine Sun |
Limited injection |
1600-1900 |
injector diagnostics checkout |
Calvey/ Harkay/ Wootton/ Dooling |
No injection |
|
Friday, September 27, 2019 |
|
|
0000-2400 |
Downtime -- Replacement of SR IS1 and begin bake-out |
Multiple |
No SR Beam |
0600-1100 |
Linac RF conditioning |
RF Group |
No injection |
1100-1700 |
BTS 5x5 matrix measurements (Test in PTB) |
Borland/ Xiao/ Wootton |
Limited injection |
1700-1900 |
PAR/Booster diagnostics checkout |
Harkay/ Calvey/ Dooling |
Limited injection |
|
Saturday, September 28, 2019 |
|
|
0000-2400 |
Downtime -- Bake-out and temperature ramp down |
Multiple |
No SR Beam |
|
Sunday, September 29, 2019 |
|
|
0000-0830 |
Bake-out rampdown |
Multiple |
No SR Beam |
The following portion of the schedule is tentative. The recovery and studies may occur earlier or later and are dependent on the replacement and testing of S:IS1. Storing beam is also dependent on vacuum. |
|||
0830-1000 |
Leak check and bake-out teardown |
Multiple |
No SR Beam |
1000--1130 |
Final survey and alignment check |
Survey |
No SR Beam |
1130-1530 |
Reassemble/reconnect equipment. Verification measurements/test on pulsed upplies |
Multipe |
No SR Beam |
1530-1630 |
Shielding verification of Zones A & F |
HP |
No SR Beam |
1630-1700 |
Search Zones A &F |
OPS |
No SR Beam |
1700-1800 |
Rack in switchgear |
FAC |
No SR Beam |
1800-2000 |
Recover SR DC power supplies, RF and Booster ramping supplies |
OPS |
No SR Beam |
1800-1900 |
Pulsed power supply testing |
P.S. Group |
No SR Beam |
1900-2000 |
Check-out SR Dipole |
P.S. Group |
No SR Beam |
2000-2200 |
Verify injection and slowly ramp up current to 102mA -- based on RF cavity vacuum |
Emery/OPS |
No SR Beam |
2200-2400 |
BPLD validation |
Sereno |
Stored beam & injection |
|
Monday, September 30, 2019 |
|
|
0000-0400 |
Lattice set-up |
Xiao |
Stored Beam & Injection |
0400-0800 |
Orbit set-up |
Yipeng Sun |
Stored Beam & injection |
0800-1000 |
Final pinhole camera set-up |
Yang |
Stored Beam & Injection |
1000-1300 |
Bunch purity setup |
Harkay |
Stored Beam & Injection |
1300-1400 |
Investigate/repair LTP:Q6 |
Puttkammer |
No injection |
1430-1700 |
Booster controllaws |
Calvey/ Harkay |
Limited injection |
1630-1830 |
IS1 Feedforward |
Emery |
Stored Beam & injection |
1830-2400 |
TBD |
|
|
|
Tuesday, October 1, 2019 |
|
|
0000-0630 |
TBD |
|
Stored Beam & injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored beam & injection |