Machine Studies
Draft Schedule for Run03-7, 2019
November 11th 0800 – November 12th 0800
Time | Descriptions | Studiers | SR Status |
| Monday, November 11, 2019 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0930 | Gap Scans and update IDGapFF look-up tables | Hahne | Stored Beam & Injection |
0930-1130 | Linac console test (07-15) | Fystro/ Berkland | Limited Injection |
0930-1130 | SR converter swap safety observation | Puttkammer | No Beam |
0930-1130 | Inspect/trace SR Interlock cables for Zone A | Ruan | No Beam |
0930-1130 | Troubleshoot S36 DCCT | Keane | No Beam |
1000-1130 | PAR fundamental digital LLRF testing | Berenc | Limited Injection |
1100-1200 | Change out Pre-Amp phase shifter at L5 | Meyer | Limited Injection |
1200-1330 | PAR fundamental digital LLRF testing with Beam | Berenc | Limited Injection |
1200-1500 | Test TFB with 324 fill pattern | Yao/DiMonte | Limited Injection |
1330-1500 | Injector training (07-15) | LaBuda/Orne | Limited Injection |
1500-1800 | L3 charge optimization | Shang/ YineSun | Limited Injection |
1800-2200 | APS-U BPM study | Sereno et al. | Stored Beam & Injection |
2200-2300 | Injector training (15-23) | Weyer/Berg | Limited Injection |
2300-2400 | Hybrid Injection Optimization | Emery/Xiao | Stored Beam & Injection |
| Tuesday, November 12, 2019 |
|
|
0000-0200 | Hybrid Injection Optimization | Emery/Xiao | Stored Beam & Injection |
0200-0700 | 6 GeV setup | Emery/Xiao | Stored Beam & Injection |
0700-0800 | Prepare for User beam | OPS | Stored Beam & Injection |