Draft Schedule for Run01-15, 2020
May 4th 0800 – May 5th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, May 4, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
1000-1200 |
Inspect L4 for PFN capacitor oil leaks |
Cours |
No Injection |
1000-1200 |
Replace RG1 water pump |
Wright |
No injection |
1000-1200 |
Repair PAR Fundamental #1 |
RF Group |
No injection |
1000-1200 |
Test Linac LLRF power supply alarms with L1RF and L4RF |
Pietryla/Fystro |
No Injection |
1030-1130 |
Check for water leak around S23 |
Bechtold |
Access Zone C |
1400-1700 |
BTS response measurement and app test |
Yao, Shang |
Limited inj. |
1700-1730 |
Verify/Set-up TFB for 24 singlets |
Harkay, Yao |
Stored beam & inj/ |
1730-1930 |
Upgrade to ESnet -- brief disruption for Argonne external connectivity. |
-- |
-- |
1730-1930 |
SR training (15-23) |
Weyer/Orne |
Stored beam & injection |
1930-2300 |
Study 24-bunch purity with PAR bunch cleaning amplifier issue |
Harkay |
Stored beam & inj. |
2300-2400 |
Tcav/PCgun study |
Yine Sun |
No injection |
|
Tuesday, May 5, 2020 |
|
|
0000-0300 |
Tcav/PCgun study (continued) |
Yine Sun |
No injection |
0300-0500 |
OPEN |
|
|
0500-0700 |
SR training (23-07) |
Grodecki/Berg |
Limited Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |