Machine Studies
Draft Schedule for Run01-2, 2020
February 3rd 0800 – February 4th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 3, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1130 |
Replace status relay for S2:C:BM |
Jordan |
No Beam |
0930-1200 |
Replace Magnet 2 P.S. in RF5 |
Trento |
No injection |
0930-1130 |
Replace faulty strobe for P4 kicker |
Donkers |
No Injection |
0930-1300 |
Set-up RG1 |
Yine Sun |
No injection |
0930-1015 |
Set-up for Zone F access |
OPS/FAC |
No beam |
1015-1100 |
Replace RF cavity blower in S36 |
MOM group |
Zone F access |
1015-1100 |
Troubleshoot erroneous indication for gap closed going to EPS -- Parasitic to Zone F access above |
Grimmer |
Zone F access |
1100-1200 |
Recover from access |
OPS/FAC |
No beam |
1300-1400 |
Check bypass valves in S36 |
Emery/Swetin |
Stored beam |
1300-1500 |
Booster training (07-15) |
Berg/Grodecki |
Limited Injection |
1400-1600 |
Test DSP boards on iocs1fb |
S. Xu |
Stored Beam & Occ. inj. |
1600-1900 |
Libera BPM timing setup testing |
Sereno |
Stored Beam & Inj. |
1900-2200 |
High resolution bunch purity checkout and abort kicker checkout |
Harkay, Yang |
Stored beam & inj. |
2200-2300 |
Check septum roll |
Emery |
Stored beam & injec. |
2300-2400 |
BTS trajectory study |
Emery |
Stored beam & inj. |
|
Tuesday, February 4, 2020 |
|
|
0000-0100 |
BTS trajectory study (cont) |
Emery |
Stored beam & inj. |
0100-0300 |
Booster training (23-07) |
Berkland/Ronzhin |
Limited injection |
0300-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |