Machine Studies

Draft Schedule for Run01-5, 2020

February 24th 0800 – February 25th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 24, 2020



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

Install new 10W amplifier and reset synthesizer

Smith

Limited Injection

0930-1130

Investigate noise peaks in y input spectrum of TFB (needs to change RF frequency

Yao, DiMonte

No beam

1000-1100

Update Controls Linux cluster

Shoaf/Robinson

No Impact Expected

1000-1100

FE shutter troubleshooting at 30ID

White/MOM

Access Zone E

1000-1100

Switch from Pump 521 to back-up (SR)

Wright

No beam

1000-1100

Switch from back-up to pump 301 (booster)

Wright

No beam

1100-1130

Recover SR

OPS

Stored beam & inj.

1130-1430

Test and setup TFB system with 24 singlet fill pattern

Yao, Dimonte

Stored beam & inj.

1430-1930

Characterization of the APSU prototype BPM electronic

Brill, Sereno, Cheng, Carwardine, Leban, Bogataj

Stored beam & inj.

1930-2330

lifetime studies at 6 GeV

Borland, Xiao

Stored beam & Occ. in.

1930-2130

Booster training (15-23)

Orne/Weyer

Limited injection

2330-2400

On-axis injection experiment

Xiao

Stored Beam & inj.


Tuesday, February 25, 2020



0000-0530

On-axis injection experiment (cont.)

Xiao

Stored Beam & inj.

0530-0700

Booster training (23-07)

Berg/Grodecki

Limited Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection