Machine Studies

Draft Schedule for Run01-6, 2020

March 2nd 0800 – March 3rd 0800



Time

Descriptions

Studiers

SR Status


Monday, March 2, 2020



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

Replace S32A:S3 power supply

Puttkammer

No beam

0930-1130

Replace blown 3A output filter fuse for 27B:H4 &27B:H4 power supplies

Puttkammer

No beam

1000-1100

Adjust manual leak rate for gas injection

Calvey/Vac Group

Access Zone D

1130-1200

Recover from SR access/work

OPS

Stored beam & inj.

1200-1500

Investigation noises in the TFB system

Yao, DiMonte

Stored beam & occ. inj.

1200-1400

Linac training (07-15)

LaBuda/Kimbro

Limited inj.

1500-1600

Set-up canting for 2-ID

Emery

Stored Beam & Inj.

1600-1800

Adjust manual leak rate for gas injection

Calvey/Vac Group

Access Zone D

1600-1800

Booster training (15-23)

Ronzhin/Berg

Stored Beam & Injection

1800-2300

gas injection study at 100 mA

Calvey, Emery, Hoyt

Stored Beam & injection

2300-2400

6GeV lifetime study

Borland

Stored beam 7 Occ. inj.


Tuesday, March 3, 2020



0000-0300

6GeV lifetime study (cont)

Borland

Stored beam 7 Occ. inj.

0000-0200

Booster training (23-07)

Orne/Weyer

Limited inj.

0300-0700

Orbit recovery for 324 singlets

Xiao

Stored beam & inj.

0700-0800

Prepare for User beam (324 singlets)

OPS

Stored Beam & Injection