Machine Studies
Draft Schedule for Run01-6, 2020
March 2nd 0800 – March 3rd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 2, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Replace S32A:S3 power supply |
Puttkammer |
No beam |
0930-1130 |
Replace blown 3A output filter fuse for 27B:H4 &27B:H4 power supplies |
Puttkammer |
No beam |
1000-1100 |
Adjust manual leak rate for gas injection |
Calvey/Vac Group |
Access Zone D |
1130-1200 |
Recover from SR access/work |
OPS |
Stored beam & inj. |
1200-1500 |
Investigation noises in the TFB system |
Yao, DiMonte |
Stored beam & occ. inj. |
1200-1400 |
Linac training (07-15) |
LaBuda/Kimbro |
Limited inj. |
1500-1600 |
Set-up canting for 2-ID |
Emery |
Stored Beam & Inj. |
1600-1800 |
Adjust manual leak rate for gas injection |
Calvey/Vac Group |
Access Zone D |
1600-1800 |
Booster training (15-23) |
Ronzhin/Berg |
Stored Beam & Injection |
1800-2300 |
gas injection study at 100 mA |
Calvey, Emery, Hoyt |
Stored Beam & injection |
2300-2400 |
6GeV lifetime study |
Borland |
Stored beam 7 Occ. inj. |
|
Tuesday, March 3, 2020 |
|
|
0000-0300 |
6GeV lifetime study (cont) |
Borland |
Stored beam 7 Occ. inj. |
0000-0200 |
Booster training (23-07) |
Orne/Weyer |
Limited inj. |
0300-0700 |
Orbit recovery for 324 singlets |
Xiao |
Stored beam & inj. |
0700-0800 |
Prepare for User beam (324 singlets) |
OPS |
Stored Beam & Injection |