Draft Schedule for Run01-8, 2020
March 16th 0800 – March 18th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 16, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
RF waveguide switch |
RF Group |
No Beam |
0930-1030 |
Install jumper in S36 DCCT |
Keane |
No Beam |
1000-1030 |
PSS End to End test 2ID |
McNamara |
No Beam |
1000-1400 |
Repair leak at 33ID PS1 |
Bechtold |
Access Zone E |
1000-1130 |
Booster console test |
Berkland/Fystro |
Limited Injection |
1030-1100 |
|
|
|
1030-1100 |
|
|
|
1130-1200 |
|
|
|
1400-1500 |
Recovery from SR accesses |
Sereno |
Stored beam & injection |
|
|
|
|
1500-1800 |
Set-up TFB for various fill patterns |
Yao |
Stored beam & occ. inj. |
|
|
|
|
1800-2200 |
Set up modified top-up for 324 singlets |
Emery |
Stored beam & inj. |
2200-2400 |
HSCU measurements |
Sajaev |
Stored bean & occ. inj. |
|
Tuesday, March 17, 2020 |
|
|
|
|
|
|
|
|
|
|
0200-0600 |
6 GeV lifetime studies |
Borland, Emery |
Stored beam & occ. inj. |
0600-0900 |
Set-up hybrid lattice |
Sajaev |
Stored beam & inj. |
0900-1000 |
Set-up 48 singlet for User study |
Emery or designee |
Stored beam & inj. |
1000-1600 |
48 singlets, Top-up, 102mA, 7 GeV study (shutter permit needed) |
Multiple beamlines, OPS |
Stored beam & inj. |
1600-2100 |
Recover orbit for hybrid fill & set up TFB |
Xiao, Yao |
Stored beam & inj. |
2100-2400 |
6 GeV lifetime studies |
Borland |
Stored beam & inj. |
|
Wednesday, March 18, 2020 |
|
|
0000-0100 |
6 GeV lifetime studies (continued) |
Borland |
Stored beam & inj. |
0100-0630 |
HSCU Orbit Bump Scan |
Sajaev |
Stored beam & inj. |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |