Draft Schedule for Run01-9, 2020

March 23rd 0800 – March 24th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 23, 2020



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno (home)

Stored Beam & Injection

0930-1030

Pump 521 & 533 switch (S22-25, S34-S37 P.S. at 0A)

Wright

No Beam

0930-1030

Troubleshoot RF4 cold cathode trip

RF Group

No Beam

1030-1100

Recover SR

OPS

Stored Beam & inj.

1100-1500

6GeV instability and lifetime studies

Borland, Emery

Stored Beam & occ. inj.

1500-1700

Test TFB for single bunch or hybrid mode

Yao, Emery

Stored Beam & inj.

1700-2100

Investigate injection efficiency for low charge and single bunch limit for hybrid

Emery, Sajaev

Stored Beam & Inj.

2100-2400

PAR Scrubbing at 7nC @ 2 Hz-- other studies may preempt this study

Follow High-charge MCR procedure

OPS

No injection


Tuesday, March 24, 2020



0000-0300

PAR Scrubbing at 7nC (continued)

OPS

No injection

0000-0700

OPEN (Continue PAR scrubbing if not used)



0700-0800

Prepare for User beam

OPS

Stored Beam & Injection