Machine Studies
Draft Schedule for Run02-1, 2020
June 8th 0900 – June 10th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 8, 2020 - Prestudies |
|
|
|
Final network work |
IT |
Must be done prior to 08:00 |
0700-1000 |
IOC & timing system checkout |
Controls |
|
0800-0900 |
Final walkthroughs All Machines |
|
All technical groups |
|
Secure All Tunnels |
Ops |
|
1000-1030 |
Restore all timing parameters |
Ops |
After CTLs work |
1000-1200 |
Rack in switchgear |
FAC |
After Ops secures tunnels |
1200-1400 |
ACIS shutdown validations |
Ops, PS, RF |
|
1400-2400 |
PS testing |
PS group |
HET dipoles must be coordinated w/ MCR |
1400-2400 |
RF testing |
RF Group |
|
|
ACIS “live tests” |
OPS |
As appropriate |
1400-1800 |
ID testing |
Grimmer |
PS & RF testing can be done at the same time |
|
Tuesday, June 9, 2020 |
|
|
0000-0900 |
Beam through the injectors |
Fystro & others |
Injector beam only |
0700-0900 |
Replace any P.S. that failed testing |
PS Group |
No beam |
0700-0850 |
MPS testing. At end set MPS hardware limit to 125mA |
|
|
0850-0900 |
Do MPS Current Monitor (I status) test |
OPS |
Stored beam & inj. |
0900-1300 |
BPLD Validations, BPM sanity check, add S26A:H3 back to RTFB (20mA) |
Sereno |
Stored beam & inj. |
1300-1500 |
Measure tunes, chromaticity, improve injection efficiency (20 mA) |
Emery |
Stored beam & inj. |
1500-1700 |
Slow fill to 115 mA 324 bunches. Contact Schroeder or Flood to change MPS software limit |
OPS |
Stored beam & inj. |
1700-2000 |
orbit sanity check with gap closure |
Yipeng Sun |
Stored beam & inj. |
2000-2100 |
pinhole setup 100 mA 324 bunches |
Yang |
Stored beam & inj. |
2100-2130 |
coupling setup |
Sajaev |
Stored beam & inj. |
2130-2330 |
Measure response matrix plus correction |
Sajaev |
Stored beam & inj. |
2330-2400 |
Record final tunes, lifetime for reference for operations |
Sajaev |
Store beam & inj. |
|
Wednesday, June 10, 2020 |
|
|
0000-0200 |
Verify top-up operations 102 mA. All operational controllaws, scripts running. Resolve any issues |
OPS |
Stored beam & inj. |
0200-0500 |
measure single bunch resolution of LB+ electronics in sector 27 |
Sereno, Brill |
Stored beam & inj. |
0630-0800 |
Prepare for User beam (no gaps closed) |
OPS |
Stored Beam & Injection |