Machine Studies

Draft Schedule for Run02-1, 2020

June 8th 0900 – June 10th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 8, 2020 - Prestudies




Final network work

IT

Must be done prior to 08:00

0700-1000

IOC & timing system checkout

Controls


0800-0900

Final walkthroughs All Machines


All technical groups


Secure All Tunnels

Ops


1000-1030

Restore all timing parameters

Ops

After CTLs work

1000-1200

Rack in switchgear

FAC

After Ops secures tunnels

1200-1400

ACIS shutdown validations

Ops, PS, RF


1400-2400

PS testing

PS group

HET dipoles must be coordinated w/ MCR

1400-2400

RF testing

RF Group



ACIS “live tests”

OPS

As appropriate

1400-1800

ID testing

Grimmer

PS & RF testing can be done at the same time


Tuesday, June 9, 2020



0000-0900

Beam through the injectors

Fystro & others

Injector beam only

0700-0900

Replace any P.S. that failed testing

PS Group

No beam

0700-0850

MPS testing. At end set MPS hardware limit to 125mA



0850-0900

Do MPS Current Monitor (I status) test

OPS

Stored beam & inj.

0900-1300

BPLD Validations, BPM sanity check, add S26A:H3 back to RTFB (20mA)

Sereno

Stored beam & inj.

1300-1500

Measure tunes, chromaticity, improve injection efficiency (20 mA)

Emery

Stored beam & inj.

1500-1700

Slow fill to 115 mA 324 bunches. Contact Schroeder or Flood to change MPS software limit

OPS

Stored beam & inj.

1700-2000

orbit sanity check with gap closure

Yipeng Sun

Stored beam & inj.

2000-2100

pinhole setup 100 mA 324 bunches

Yang

Stored beam & inj.

2100-2130

coupling setup

Sajaev

Stored beam & inj.

2130-2330

Measure response matrix plus correction

Sajaev

Stored beam & inj.

2330-2400

Record final tunes, lifetime for reference for operations

Sajaev

Store beam & inj.


Wednesday, June 10, 2020



0000-0200

Verify top-up operations 102 mA. All operational controllaws, scripts running. Resolve any issues

OPS

Stored beam & inj.

0200-0500

measure single bunch resolution of LB+ electronics in sector 27

Sereno, Brill

Stored beam & inj.

0630-0800

Prepare for User beam (no gaps closed)

OPS

Stored Beam & Injection