Draft Schedule for Run02-12, 2020

September 28th 0800 – October 1st 0800

 

Time

Descriptions

Studiers

SR Status

 

Monday, September 28, 2020

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1000

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

1000-1100

Troubleshoot pump 405 affects S1&2

Wright

No Beam

1000-1200

Troubleshoot iochdg1

Pietryla

Limited Injection

1000-1200

Install canted correctors PS at 25ID

Vargas

No Beam

1030-1130

Valve off S25 GRID  BPM / thermocouple work

MOM/Erwin

Access Zone D

1030-1100

Replace IR detector at S38

MOM

Access Zone F

1200-1300

Test of BPLD validation script

Sereno/Shang

Stored Beam & Injection

1300-1800

S25 GRID  BPM studies

Yang, et al

Limited Injection

1300-1600

BTS arrival time detector

Sereno, et al

Limited Injection

1600-1800

PAR training (15-23)

Ronzhin/Kimbro

Limited Injection

1800-2400

6 GeV single and multi bunch instability thresholds

Emery/Lindberg

Stored Beam & Injection

 

Tuesday, September 29, 2020

 

 

0000-0600

RG1 beam tune up

Y.E. Sun

Limited Injection

0600-0700

Booster currMon signal beam charge scan

Yao

Stored Beam & Injection

0700-0900

BTS response measurement

Yao/Shang

No Beam

0900-0930

Cable inventory

Dooling

Access Linac

0900-1100

Test canted correctors PS at 25ID

Jordan

No Beam

0900-1200

Waste management/IH assess PAR

WM/McGhee

Access PAR

0900-1300

RF-5 conditioning RF / waveguide switch

RF Group

Limited Injection

1300-1500

Measure SR orbit noise with water sound dampener in S37 off and on. And switch pumps too.

Emery/Wright

Stored Beam & Injection

1500-1600

Test Labca for APS

Huang/Y.P. Sun

Stored Beam & Injection

1600-1800

PAR training (15-23)

Ronzhin/Kimbro

Limited Injection

1600-1700

Orbit switch procedure improvements

Y.P. Sun/Shang

Limited Injection

1800-2100

Booster chrom correction test

Yao/Shang

No Beam

2100-2400

Booster emittance measurements vs momentum offset

Harkay, et al

No Beam

 

Wednesday, September 30, 2020

 

 

0000-0300

Booster emittance measurements vs momentum offset

Harkay, et al

No Beam

0300-0900

RG1 Beam tune up

Y.E. Sun

Limited Injection

0900-1300

S27-28 FBC Fast Corrector Step Response measurement

Sereno, et al

Stored Beam & Injection

1300-1700

Sextupole offset measurement

Sajaev

Stored Beam & Injection

1700-2000

Turn-by-Turn BPM data taking

Huang/Sajaev/ Y.P.Sun

Stored Beam & Injection

2000-2300

Orbit switch procedure improvements

Y.P. Sun/Shang

Limited Injection

2000-2200

PAR training (15-23)

Ronzhin/Kimbro

Limited Injection

2300-2400

6 GeV dimtel x-plane feedback

Emery/Kallakuri

Stored Beam & Injection

 

Thursday, October 1, 2020

 

 

0000-0300

6 GeV dimtel x-plane feedback

Emery/Kallakuri

Stored Beam & Injection

0300-0600

6 GeV ID perturbation measurement

Emery

Stored Beam & Injection

0600-0700

Open

 

 

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection