Draft Schedule for Run02-7, 2020

July 27th 0800 – July 28th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 27, 2020



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1000

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

1000-1100

RF waveguide switch

RF Group

No Beam

1000-1200

Troubleshoot Booster Pump 301 motor controller sams unit and place back on-line, (affects Booster RF cavities, Booster Inj. Pulsed Supplies, all Booster P.S., PTB dipoles)

Wright, FAC

No injection

1000-1300

Relocate diagnostics equipment

Blake

Stored Beam & Injection

1200-1400

SR console test (07-15)

Schroeder/Berg

Stored Beam & Injection

1400-1700

Booster chrom tuning study

Yao

Occ. Inj. possible

1700-1900

P0FB 24 singlet setup test.

Yao, Emery

Stored Beam & inj.

1900-2100

6 GeV single bunch and multi-bunch thresholds

Emery

Stored Beam & inj.

2100-2300

test and put bpms back in datapool/RTFB and realign S27 GRID XBPM

Sereno

Stored Beam & inj.

2300-2400

SR training (23-07)

Weyer/Berkland

Stored Beam and Injection


Tuesday, July 28, 2020



0000-0100

SR training (23-07) (continued)

Weyer/Berkland

Stored Beam and Injection

0100-0700

OPEN



0700-0800

Prepare for User beam

OPS

Stored Beam & Injection