Draft Schedule for Run02-7, 2020
July 27th 0800 – July 28th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 27, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
1000-1100 |
RF waveguide switch |
RF Group |
No Beam |
1000-1200 |
Troubleshoot Booster Pump 301 motor controller sams unit and place back on-line, (affects Booster RF cavities, Booster Inj. Pulsed Supplies, all Booster P.S., PTB dipoles) |
Wright, FAC |
No injection |
1000-1300 |
Relocate diagnostics equipment |
Blake |
Stored Beam & Injection |
1200-1400 |
SR console test (07-15) |
Schroeder/Berg |
Stored Beam & Injection |
1400-1700 |
Booster chrom tuning study |
Yao |
Occ. Inj. possible |
1700-1900 |
P0FB 24 singlet setup test. |
Yao, Emery |
Stored Beam & inj. |
1900-2100 |
6 GeV single bunch and multi-bunch thresholds |
Emery |
Stored Beam & inj. |
2100-2300 |
test and put bpms back in datapool/RTFB and realign S27 GRID XBPM |
Sereno |
Stored Beam & inj. |
2300-2400 |
SR training (23-07) |
Weyer/Berkland |
Stored Beam and Injection |
|
Tuesday, July 28, 2020 |
|
|
0000-0100 |
SR training (23-07) (continued) |
Weyer/Berkland |
Stored Beam and Injection |
0100-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |