Machine Studies
Draft Schedule for Run02-8, 2020
August 3rd 0800 – August 4th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, August 3, 2020 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
1000-1300 |
Investigate interstation phase shifts |
RF Group |
No Beam |
1300-1500 |
SR console testing |
Orne/Schroeder |
Stored Beam & Injection |
1500-1800 |
Put bpms in datapool and RTFB and commission BTS beam arrival time monitor |
Sereno, Erwin |
Stored Beam & Injection |
1800-2000 |
Linac operator training (15-23) |
Ronzhin/Kimbro |
Limited Inj. |
2000-2200 |
test new Booster chrom tuning program. Booster beam need to change rf frequency |
Yao, Shang |
No Stored Beam |
2200-2400 |
check SR vertical beam instability and P0FB settings. |
Yao |
Stored Beam & Inj. |
|
Tuesday, August 4, 2020 |
|
|
0000-0300 |
6 GeV. measure pinhole resolution with low-vertical emittance beam. |
Emery, Xiao |
Stored beam & inj. |
0300-0700 |
Practical beam measurement at 6GeV |
Xiao |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |