Draft Schedule for Run03-10, 2020
December 17th 0800 – December 17th 2400
Time | Descriptions | Studiers | SR Status |
Thursday, December 17, 2020 | |||
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0900 | Operator re-qualification | Grodecki/Schroeder | Stored Beam & Injection |
0900-1600 | Timing & Synch related rf Studies with possible Topup running | Wienands, et al. | Stored Beam & Injection |
1600-1700 | SR recovery | Emery | Stored Beam & Injection |
1700-2130 | Independent booster cavity calibration | Calvey/Berenc/ Harkay | No Injection |
2130-2200 | SR injection check out | Calvey/Berenc/ Harkay | Stored Beam & Injection |
2200-2400 | “Gentle shutdown” of SR | OPS | No Beam |