Machine Studies

Draft Schedule for Run03-2, 2020

October 12th 0800 – October 13th 0800



Time

Descriptions

Studiers

SR Status


Monday, October 12, 2020



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

0930-1030

RF waveguide switch

RF Group

No Beam

0930-1030

Replace blower at RF-2

MOM

No Beam

0930-1030

Vent Yokogawa at 35ID

Moonier

No Beam

0930-1100

Update injector iocs(iochdg1, iochbpm1, ioclic3)

Pietryla

Limited Injection

0930-1130

Investigate the cause of crowbar trips at RF5 and calibrate Bergoz card current readback Test LLRF boards in RF5

RF Group

Limited Injection/No Beam

1015-1100

S:BM temperature reading

Jordan

Access Zone C

1130-1600

RF-5 measurements A-B phase measurements

RF Group

Limited Injection

1100-1300

SR recovery and inject 324 (when rf work permit)

OPS

Limited Injection

1300-1400

BPLD validation script test

Sereno/Shang

Limited Injection

1400-1600

Reboot iocs25fb to test database and P0/P1 calibration factors

Xu/Sereno

Limited Injection

1600-1700

Measure noise and check calibration of the BTS current monitor

Keane

Limited Injection

1700-1900

Booster chrom correction test

Yao/Shang

No Beam

1900-2100

Abort kicker checkout

Harkay

Stored Beam & Injection

2100-2300

Tune change from standardization of magnets

Emery

Stored Beam & Injection

2300-2400

RG1 beam tune up

Y.E. Sun/Fystro

Limited Injection


Tuesday, October 13, 2020



0000-0500

RG1 beam tune up

Y.E. Sun/Fystro

Limited Injection

0500-0700

Tune change from IEX

Xiao

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection