Machine Studies

Draft Schedule for Run03-7, 2020

November 16th 0800 – November 17th 0800

 

Time

Descriptions

Studiers

SR Status

 

Monday, November 16, 2020

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

SR Gaps scans

Hahne

Stored Beam & Injection

0930-1130

Troubleshoot S17 PS communications

Puttkammer

No Beam

0930-1030

Switch from P-525 to back-up pump (P.S. in S26 through S29 set to 0)

Wright

No Beam

1000-1100

Inspect interferences for PAR shielding

Harkay, Dwyer

Access PAR

1030-1100

S35 gas study mapping

Dooling/Gagliano

Access Zone E

1100-1200

Recover SR and Injectors

Ops

Stored Beam & Injection

1200-1500

LB+ single bunch measurements / MOMBO scan square matrix testing / topup monitor PV testing

Sereno/Adam

Stored Beam & Injection

1500-1800

S27 FBC testing

Sereno/Carwardine/Sirisha/Adam

Limited Injection

1500-1800

L3:CM1 charge optimization test

Shang/Y.E. Sun/ Song/Huang

Limited Injection

1800-2100

Test IEX FF script

Xiao

Limited Injection

1800-2000

Take BTS BPM response with B2C8V corrector bump

Yao/Shang

Booster Beam

2000-2100

Test Booster B3C3 BPM history

Yao/Pietryla

Booster Beam

2100-2400

SR beta-beating study

Y.P. Sun

Stored Beam & Injection

 

Tuesday, November 17, 2020

 

 

0000-0400

DA optimization with new software

Emery/Shang/Huang

Stored Beam & Injection

0400-0700

6 GeV ID perturbation

Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection