Draft Schedule for Run03-8, 2020
November 25th 0800 – November 27th 0800
Time | Descriptions | Studiers | SR Status |
| Wednesday, November 25, 2020 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0930 | SR Gap scans | Hahne | Stored Beam & Injection |
0930-1030 | RF waveguide switch | RF Group | No Beam |
0930-1130 | Investigate communication loss S17 | Puttkammer | No Beam |
1030-1130 | Test PAR RF-12 into cavity | T. Smith | Limited Injection |
1030-1230 | RF-3 water loop tuning | Swetin | Limited Injection |
1130-1330 | PAR training (07-15) | Kimbro/Ronzhin | Limited Injection |
1230-1330 | Investigate RF-5 filament OI interlock | RF Group | Limited Injection |
1330-1400 | SR recovery | OPS | Stored Beam & Injection |
1400-1900 | Orbit switch | Y.P. Sun | Stored Beam & Injection |
1900-2200 | 6 GeV ID perturbation measurement | Emery | Stored Beam & Injection |
2200-2300 | SR Operator re-qualification | Davis/Schroeder | Stored Beam & Injection |
2300-2400 | SR Operator re-qualification | LaBuda/Schroeder | Stored Beam & Injection |
| Thursday, November 26, 2020 |
|
|
0000-0600 | Testing IEX FF table | Xiao | Limited Injection |
0000-0200 | Booster TBT beam history | Yao | Limited Injection |
0200-0600 | Align booster sextupole timing and optimize injection | Yao | Limited Injection |
0600-1400 | APS-U timing set up | Wienands/CTLS | No Beam/Stored Beam & Injection but with altered timing |
1400-1500 | SR Operator re-qualification | Ronzhin/Schroeder | Stored Beam & Injection |
1500-1600 | SR Operator re-qualification | Weyer/Schroeder | Stored Beam & Injection |
1600-2400 | Mombo XBPM gap scan | Sereno | Stored Beam & Injection |
| Friday, November 27, 2020 |
|
|
0000-0400 | Injection optimization | Shang/Emery/Huang | Stored Beam & Injection |
0400-0630 | SR optimization | Y.P. Sun | Stored Beam & Injection |
0630-0800 | Prepare for User beam | OPS | Stored Beam & Injection |