Machine Studies
Draft Schedule for Run01-1, 2021
January 19th 0800 – January 26th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, Jan. 18, 2021 - Prestudies |
|
|
0700-0900 |
MPS Validations |
Smith/Flood |
No injection |
0900-1000 |
Prepare SR for RF Conditioning with beam |
Flood/OPS |
Stored beam & inj. |
1000-2400 |
RF Conditioning with Beam (24 singlets) |
OPS |
Stored beam & inj. |
~1500 |
Pinhole camera initial set-up (current above 50mA) parallel to RF conditioning w/beam |
Yang |
Stored beam & inj. |
~1700 |
BPM checkout (parallel to RF conditioning w/ beam |
Sereno |
Stored beam & inj. |
|
Tuesday, January 19, 2021 |
|
|
0000-0800 |
RF Conditioning with beam |
OPS |
Stored beam & inj. |
0800-1200 |
BPLD Validations |
Sereno |
Stored beam & inj. |
1200-1400 |
X-BPM Sanity Check |
Sereno |
Stored beam & inj. |
1400-2000 |
Lattice set-up |
Xiao |
Stored beam & inj. |
2000-2400 |
Orbit recovery |
Yipeng Sun |
Stored beam & inj. |
|
Wednesday, January 20, 2021 |
|
|
0000-0100 |
Orbit recovery (continued) |
Yipeng Sun |
Stored beam & inj. |
0100-0700 |
RG1 conditioning |
Yine Sun |
No injection |
0100-0700 |
CPU/IEX checkout |
Xiao, OPS |
Stored beam & occ. inj. |
0700-0900 |
Test B3C2P1 and B3C2P2 BPMs after configuration change |
Yao, Pietryla |
Limited inj. |
0900-1100 |
Booster singleTurn injection x-controllaw setup |
Yao, Shang |
Limited inj. |
0900-1400 |
SR Lifetime study (parasitic to Booster studies) |
Yipeng Sun |
Stored beam & inj. |
1100-1400 |
Booster chrom optimization with SD/SF new ramps. |
Yao, Shang |
Limited inj. |
1400-1500 |
Operator requalification |
Grodecki, Schroeder |
Stored beam & inj. |
1500-1700 |
Operator requalification |
Smith, Schroeder |
Stored beam & inj. |
1700-1900 |
Booster tune-up |
Calvey |
Stored beam & inj. |
1900-2300 |
Set-up optics correction for new 6 GeV lattice |
Emery, Xiao |
Stored beam & inj. |
2300-2400 |
ID Steering & BPM offset measurement |
Xiao |
Stored beam & occ. inj. |
|
Thursday, January 21, 2021 |
|
|
0000-0500 |
ID Steering & BPM offset measurement (continued) |
Xiao |
Stored beam & occ. inj. |
0500-1030 |
RG1 beam in linac optimization |
Yine Sun, Shang |
No injection |
0700-0800 |
Prepare for SR access |
OPS |
No beam |
0800-0900 |
Check in-tunnel connections for S26B:P1 |
Blake |
Access Zone D |
1030-1130 |
BPLD Validation for 26B:P1 if needed |
Sereno |
Stored beam & inj. |
1130-1300 |
Injector training |
Kimbro, Grodecki |
Limited inj. |
1300-2300 |
Timing & synch test |
Wienands, et al |
Stored beam & inj. |
2300-2400 |
Accumulation limit as a benchmark of performance (hybrid setup) |
Xiao/Emery |
Stored beam & inj. |
|
Friday, January 22, 2021 |
|
|
0000-0500 |
Accumulation limit as a benchmark of performance (hybrid setup) (continued) |
Xiao/Emery |
Stored beam & inj. |
0500-1100 |
RG1 beam lattice matching, PAR injection optimization, control law set up and beam stability measurements |
Yine Sun, Fystro |
No injection |
1100-1300 |
testing booster x-injection controllaw with beam |
Calvey, Fystro, Yao Shang |
No injection |
1300-1500 |
Injector training |
Grodecki, Kimbro |
Limited injection |
1300-1500 |
SR Lifetime study |
Yipeng Sun |
Stored beam |
1500-1700 |
Booster TBT history with rf ramp and Ext kicker as pinger |
Yao |
No injection |
1700-1900 |
Check PC gun transmission through Linac |
Dooling |
No injection |
1900-2300 |
optimize injection of the above 6 GeV lattice |
Emery, Shang, Huang. |
Stored beam & inj. |
2300-2400 |
vertical scan of scraper for lifetime. |
Emery |
Stored beam & inj. |
|
Saturday, January 23, 2021 |
|
|
0000-0100 |
vertical scan of scraper for lifetime.(continued) |
Emery |
Stored beam & inj. |
0300-1000 |
Top-up verification (24 singlets,gaps closed, all controllaws running) |
OPS |
Stored beam & injection |
1000-1600 |
CPU/IEX correction |
Xiao |
Stored beam & inj. |
1600-2000 |
6GeV Undulator Perturbation |
Emery |
Stored beam & inj. |
2000-2400 |
Top-up verification (24 singlets,gaps closed, all controllaws running) - 6 hours with interleaving |
OPS/Dooling |
Stored beam & inj. |
|
Sunday, January 24, 2021 |
|
|
0000-1000 |
Top-up verification (continued) |
OPS |
Stored beam & inj. |
1000-1500 |
6 GeV single bunch limit |
Emery |
Stored beam & inj. |
1500-2000 |
Online optimization with TBT BPM |
Yipeng Sun |
Stored beam & inj |
2000-2200 |
Abort kicker checkout |
Harkay, Xiao |
Stored beam & inj. |
2200-2400 |
Final Optics Set-up |
Xiao |
Stored beam & Inj. |
|
Monday, January 25, 2021 |
|
|
0000-0200 |
Final Optics Set-up (continued) |
Xiao |
Stored beam & Inj. |
0300-0700 |
Sextupole offset measurements |
Sajaev |
Stored beam & inj. |
0800-1200 |
7 GeV Dimtel feeback testing |
Emery/Diag |
Stored beam & inj. |
1200-1400 |
P0 feedback |
Yao |
Stored beam & inj. |
1400-1800 |
Final set-up of bunch purity monitor and pinhole camera |
Yang |
Stored beam & inj. |
1800-2200 |
Final orbit set-up |
Yipeng Sun |
Stored beam & inj. |
2200-2400 |
Bunch Purity checkout |
Harkay, Yipeng Sun |
Stored beam & inj. |
|
Tuesday, January 26, 2021 |
|
|
0000-0630 |
OPEN |
|
|
0630-0800 |
Prepare for User beam (no gaps closed) |
OPS |
Stored Beam & Injection |