Machine Studies

Schedule for Run01-10, 2021

March 29th 0800 – March 30th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 29, 2021



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

28ID end to end test

McNamara

A-E controlled access

0930-1330

Bus tie switchgear X8

Doktorczyk

No impact

0930-1130

PAR BM measurements

Puttkammer

Limited Injection

0930-1300

RG1 beam study (as soon as injectors are available)

Y. Sun, Huang, Shang

Limited Injection

1300-1500

Booster console test

Fystro/Kimbro

Limited Injection

1500-1700

Booster tune measurement vs frequency shift

Yao, Shang

Limited Injection

1700-2100

BTS measurements

Xiao, Yao, Shang

Stored Beam & Injection

1700-1800

Measure bpm offsets at ID29

Emery

Stored Beam & Injection

2100-2400

Dimtel feedback check for single bunch at various chromaticities

Emery

Stored Beam & Injection


Tuesday, March 30, 2021



0000-0600

6 GeV lattice check

Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection