Machine Studies
Draft Schedule for Run01-3, 2021
February 8th 0800 – February 9th 0800
Time | Descriptions | Studiers | SR Status |
| Monday, February 8, 2021 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0930 | Gap Scans and update IDGapFF look-up tables | Hahne | Stored Beam & Injection |
0930-1000 | Reboot 6ID MOXA | Smith | No Beam |
0930-1130 | Troubleshoot S6 canted supply issues | Jordan | No Beam |
0930-1130 | Replace +5v supplies (S8,9, 11) | Vargas/Vanis | No Beam |
0930-1130 | Fix exhaust fan in SR S7 converter cabinet 1 | Meier | No Beam |
1000-1100 | PAR shielding mapping | Wienands, et al | Access PAR |
1000-1100 | ITS cable work | Meyer | Access ITS |
1030-1100 | Remove matching networks | Brill | Access Zone F |
1030-1100 | Check S38 cavity thermocouples | Wright | Access Zone F |
1100-1200 | Recover SR and injectors. Verify injection. | OPS | No Beam |
1200-1230 | Set up Dimtel in sectors 2 and 35 | Brill | 6 GeV Beam No Injection |
1200-1230 | Set up 6 GeV. Fill 324 bunches | Emery | Stored Beam & Injection |
1230-1830 | RG1 study | Yine Shang Borland Fystro Huang | 6 GeV Beam but no injection |
1230-1630 | 6 GeV studies, ID perturbation | Emery Xiao | 6 GeV Beam No Injection |
1730-1830 | Setup SR for 7 GeV. Test with injected beam a short time at 1830 | Emery Xiao | No Beam & No Injection |
1830-2130 | Booster chromaticity. Vary rf frequency. | Yao Shang | No Beam & No Injection |
2130-0130 | Dimtel feedback sector 2. Check running sector 35 and 2 together as x and y planes. | Emery Kallakuri | Stored Beam & Injection |
| Tuesday, February 9, 2021 |
|
|
0130-0500 | 6 GeV studies, single bunch instability. Use Dimtel in both planes | Emery Xiao Kallakuri | 6 GeV Beam & Injection |
0500-0600 | Connect P0 feedback, setup up for 7 GeV | Brill Emery | Stored Beam & Limited Injection |
0500-0700 | Booster training | Grodecki/Kimbro | Limited Injection |
0700-0800 | Prepare for User beam | OPS | Stored Beam & Injection |