Machine Studies
Schedule for Run01-5, 2021
February 22nd 0800 – February 23rd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 22, 2021 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1130 |
Investigate S16 communications issue |
Vargas |
No Beam |
0930-1130 |
Investigate controlled access key Zone B |
Belcher |
No Beam |
0930-1130 |
Investigate S7 canted supplies |
Jordan |
No Beam |
0930-1130 |
Measure Booster sextupole temperature readbacks |
Puttkammer |
Limited Injection |
1130-1230 |
Recover SR. Fill 24 bunches at 1230. |
OPS |
Stored Beam & Injection |
1230-1430 |
Booster training (07-15) |
Davis/Kimbro |
Limited Injection |
1230-1430 |
Orbit to rf phase feedback |
Sereno Brill Kallakuri Carwardine Wienands |
Stored Beam |
1430-1930 |
Orbit Switch. Leave 324 bunches stored for next 6 hours. |
Yipeng |
Stored Beam & Injection |
1930-2400 |
Set up PC gun for injection PAR and beyond |
Yin-e, Dooling, Fystro and others |
Stored beam and no injection |
|
Tuesday, February 23, 2021 |
|
|
0000-0130 |
Set up PC gun for injection PAR and beyond |
Yin-e, Dooling, Fystro and others |
Stored beam and no injection |
0130-0230 |
Any operational readiness items |
Emery |
Stored Beam & Injection |
0230-0630 |
Dimtel setup software tests |
Emery |
Stored Beam & Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |