Machine Studies

Schedule for Run01-6, 2021

March 1st 0800 – March 2nd 0800



Time

Descriptions

Studiers

SR Status


Monday, March 1, 2021



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1000

Switch 15ID PSS and EPS to UPS

Budz

No Beam

0930-1030

Replace RF cavity blowers

Wright

Access Zone F

0930-1030

Fix sector 25 BPLD

Brill

No Beam

1100-1230

Booster SD/SF ramp optimization. No injection, need to change rf frequency

Yao Shang

No Beam

1130-1230

Recover SR. Fill 324 bunches at 1230.

OPS

Stored Beam & Injection

1200-1300

IS1 measurements

Puttkammer

Stored Beam & Injection

1230-1630

BTS trajectory measurements (moved from Tuesday 0300)

Xiao

Stored Beam & Injection

1300-1630

Orbit to rf phase feedback

Sereno Brill Kallakuri Carwardine Wienands

Stored Beam

1630-1830

Trajectory acquisition using the TBT DAQ and LB+ bpms in sector 27

Shoaf Sereno Brill

Stored Beam & Injection

1830-2230

Sextupole optimization with new lattice

Huang Shang Emery

Stored Beam & Injection

2230-2400

Dimtel setup software tests

Emery

Stored Beam & Injection


Tuesday, March 2nd, 2021



0000-0300

Dimtel setup software tests

Emery

Stored Beam & Injection

0300-0330

S25 BPLD verification

Sereno

Stored Beam & Injection

0330-0600

Open

Xiao

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection