Schedule for Run02-1, 2021 (includes Pre-studies)
May 24th 0800 – June 2nd 0800
Time | Descriptions | Studiers | SR Status |
Monday, May 24, 2021 (Pre-Studies) | |||
0700-0900 | MPS validations | Smith/OPS | Stored beam & injection |
0900-0000 | Conditioning with beam (24 singlets) | OPS | Stored beam & injection |
~1500 | Pinhole camera initial set-up (current above 50 mA) parallel to RF conditioning w/beam | Yang | Stored beam & injection |
~1700 | BPM checkout (parallel to RF conditioning w/beam) | Sereno | Stored beam & injection |
Tuesday, May 25, 2021 | |||
0000-0800 | Conditioning with beam (24 singlets) | OPS | Stored beam & injection |
0800-1300 | (Added) Conditioning with beam (24 singlets) | OPS | Stored beam & injection |
1300-1700 | BPLD Validations | Hahne | Stored beam & injection |
1700-1900 | X-BPM Sanity Check | Hahne | Stored beam & injection |
1900-2400 | Lattice set-up | Xiao Sajaev | Stored beam & injection |
2000-2400 | Orbit recovery | Yipeng Sun | Stored beam & injection |
Wednesday, May 26, 2021 | |||
0000-0100 | Lattice set-up | Xiao Sajaev | Stored beam & injection |
0000-0100 | Orbit recovery | Yipeng Sun | Stored beam & injection |
0100-0700 | IEX/CPU checkout | OPS/Xiao | Stored beam & injection |
0700-1000 | Check and scan SR BPM singleTurn timing | Yao | Stored beam & injection |
1000-1700 | Accumulation limit as a benchmark of performance (hybrid setup) | Xiao | Stored beam & injection |
1000-1700 | Orbit recovery | Yipeng Sun | Stored beam & injection |
1700-2100 | Setup Dimtel boxes | Emery | Stored beam & injection |
2100-2400 | IEX/CPU checkout | OPS/Xiao | Stored beam & injection |
Thursday, May 27, 2021 | |||
0000-0400 | IEX/CPU checkout | OPS/Xiao | Stored beam & injection |
0400-0800 | Open | ||
0800-1000 | HET rad survey | Henry | Access Booster/ Stored Beam SR |
0800-1100 | Linac interleaving trigger validation | Pietryla | No Injection |
0800-1100 | Check 09ID PSS connection to PS2 shutter | Belcher | Zone B Access |
1100-1200 | Recover Booster/SR (324 fill) | OPS | Limited Injection |
1200-1700 | Booster cavity phasing/voltage verification | Calvey/RF group | Limited injection |
1700-2100 | Tune up RG2 beam (with RG1 alpha magnet off) | Yine Sun, Fystro | Stored beam |
1200-2100 | IEX/CPU correction | Xiao | Stored beam |
2100-2400 | Open | ||
Friday, May 28, 2021 | |||
0000-0800 | Open | ||
0800-1100 | BTS measurement | Xiao/Shang | No Injection |
0800-1100 | Investigation of RF5 | RF group | No beam |
1100-1700 | 6 GeV beam instability benchmarking | Emery | Stored beam & injection |
1700-2400 | Top-up verification (24 singlets,gaps closed, all controllaws running) | OPS | Stored beam & injection |
1700-2300 | Stored beam & injectionDoolingTest Interleaving mode with top-up running | Dooling | Stored beam & injection |
1700-2400 | Sector 35 gas injection HP surveys | Calvey/Hoyt/Heyek | Stored beam & injection |
Saturday, May 29, 2021 | |||
0000-0100 | Sector 35 gas injection HP surveys | Calvey/Hoyt/Heyek | Stored beam & injection |
0000-0600 | Top-up verification (24 singlets,gaps closed, all controllaws running) | OPS | Stored beam & injection |
0600-1000 | Various study | Xiao | Stored beam & injection |
1000-1600 | 6 GeV beam instability benchmarking | Emery | Stored beam & injection |
1600-2000 | Sector 27 orbit feedback studies - test new controllers for 3x12 irm | Sereno, et al | Stored beam & injection |
2000-2400 | Put back BPMs to XRDP/DP | Sereno | Stored beam & injection |
Sunday, May 30, 2021 | |||
0000-0800 | Open | ||
0800-1400 | Test Booster chrom correction | Yao/Shang | Stored beam |
1400-1600 | Booster tune-up | Calvey | Limited injection |
1600-1800 | Examine why 180 phase shift is required in the FIR for 6 GeV operation | Emery | Stored beam & injection |
1800-2200 | 6 GeV optimize kickers | Emery | Stored beam & injection |
2200-2400 | Open | ||
Monday, May 31, 2021 | |||
0000-0600 | Open | ||
0600-1000 | Final Lattice Setup | Xiao | Stored beam & injection |
1000-1400 | Low alpha lattice | Yipeng Sun, Huang | Stored beam & injection |
1400-1800 | Sextupole optimization | Emery/Huang/Shang | Stored beam & injection |
1800-2400 | Open | ||
1800-2400 | Top-up verification (24 singlets,gaps closed, all controllaws running) | OPS | Stored beam & injection |
1800-2400 | Test Interleaving mode with top-up running | Dooling | Stored beam & injection |
Tuesday, June 1, 2021 | |||
0000-0800 | Top-up verification (24 singlets,gaps closed, all controllaws running) | OPS | Stored beam & injection |
0800-1200 | Final set-up of bunch purity monitor and pinhole camera | Yang | Stored beam & injection |
1200-1600 | Final Lattice setup | Xiao | Stored beam & injection |
1200-1600 | Final orbit set-up | Yipeng Sun | Stored beam & injection |
1600-1800 | Bunch purity checkout | Yipeng Sun, Harkay | Stored beam & injection |
1800-2000 | Abort kicker checkout | Xiao/Harkay | Stored beam & injection |
2000-2400 | Open | ||
Wednesday, June 2 2021 | |||
0000-0630 | Open | ||
0630-0800 | Prepare for User beam | OPS | Stored beam & injection |