Draft Schedule for Run02-2, 2021
June 7th 0800 - June 8th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 7, 2021 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1100 |
SR IS1 inspection for upgrade |
Puttkammer |
No Beam |
1000-1100 |
Replace IR detector at S40 Cav3 |
Wright |
Access Zone F |
1100-1200 |
Recover SR systems |
OPS |
Stored Beam & Injection |
1200-1300 |
Diagnose S35BM pinhole camera error condition |
Yang |
Stored Beam & Injection |
1300-1700 |
Measure orbit motion spectrum with/without Dimtel system |
Carwardine, et al |
Stored Beam & Injection |
1700-2200 |
6 GeV instability |
Emery |
Stored Beam & Injection |
2200-2400 |
Sextupole optimization |
Emery/Huang/Shang |
Stored Beam & Injection |
|
Tuesday, June 8, 2021 |
|
|
0000-0200 |
Sextupole optimization |
Emery/Huang/Shang |
Stored Beam & Injection |
0200-0630 |
Low alpha lattice |
Huang/Sajaev |
Stored Beam & Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |