Draft Schedule for Run02-8, 2021

July 19th 0800 – July 20th 0800

 

Time

Descriptions

Studiers

SR Status

 

Monday, July 19, 2021

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1400

APS-U Booster RF setup

Weinands et al

Limited Injection

1400-1530

Gas experiment leakage set up

Hoyt

Access Zone E

1400-1500

RF waveguide switch

RF Group

No Beam

1530-1800

Redo BTS response measurement

Yao/Shang

Limited Injection

1800-2400

Gas Injection Study

Calvey et al.

Stored Beam & Injection

 

Tuesday, July 20, 2021

 

 

0000-0500

Acceptance testing with beam for Sparks+rf switch

Sereno/Cheng/ Brill

Stored Beam & Injection

0500-0630

Open

 

 

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection