Machine Studies

Draft Schedule for Run03-2, 2021

October 18th 0800 – October 19th 0800



Time

Descriptions

Studiers

SR Status


Monday, October 18, 2021



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0800-0900

Add B:IK trigger scope

Fors

Limited Injection

0900-2100

Replace mask at S31ID

MOM

Access Zone E

0930-1330

RF-5 troubleshooting

Berenc

Limited Injection

1000-1100

LBB power tie in Process water S23&24 down.

FAC

No Beam

1000-1200

S25 GRID X BPM repair

Blake

Access Zone D

1000-1200

S:IS1 logger testing (Zone F is in beam permit)

Shang, Fystro

Access Zone D

1100-1700

PAR requalifications

Fystro, Labuda, Grodecki, Berkland, Kimbro, Ronzhin

Limited Injection

1200-1300

Recover SR

Ops

Stored Beam & Injection

1200-1400

ExperimentDesigner tests (booster)

Shang

Stored Beam & Injection

1300-1700

Open slot for SR


Stored Beam & Limited Injection

1700-2000

6 GeV small-alpha injection improvement

Emery, Sajaev

Stored Beam & Injection

2000-2400

6 GeV small-alpha loops closed

Emery, Kallakuri

Stored Beam & Injection


Tuesday, October 19, 2021



0000-0400

6 GeV Instabilities

Emery

Stored Beam & Injection

0400-0700

Booster Chromaticity. Rf frequency change

Yao

No Beam

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection