Machine Studies

Draft Schedule for Run03-3, 2021

October 25th 0800 – October 26th 0800



Time

Descriptions

Studiers

SR Status


Monday, October 25, 2021



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Limited Injection

0810-0930

PAR requalifications (portion)

Fystro/Weyer/ Orne

Limited Injection

0930-1030

Check and fix S35 P0Feedback pre-amplifier

Zabel, Blake

No Beam

0930-1130

Measure PAR RF source switching box

Berenc

No Beam

0930-1130

Waveguide switch and RF-4 measurements I (spot-knocking, no beam)

RF Group

No beam

1130-1530

Waveguide switch and RF-4 measurements II

RF Group

Stored Beam & Injection

1130-1330

Test the PAR BDM acquisition script. PAR beam is needed

Harkay, Shang

Limited Injection

1330-1530

Put S27A bpms back into orbit correction. Parasitic to RF group’s time

Emery or Sereno

Stored Beam & Injection

1530-1930

Booster chromaticity. Large RF frequency changes

Yao, Shang

No beam

1930-2400

6 GeV beam dynamics

Emery

Stored Beam & Injection


Tuesday, October 26, 2021



0000-0500

Open


Stored Beam & Injection

0500-0700

SR training

Ronzhin/Kimbro

Stored Beam & Injection





0700-0800

Prepare for User beam

OPS

Stored Beam & Injection