Machine Studies
Draft Schedule for Run03-9, 2021
December 13th 0800 – December 14th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 13, 2021 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Replace MPV956B board in iocs40fb |
Xu |
No Beam |
0930-1130 |
Electrical measurements of S:IS |
Puttkammer |
No Beam |
1000-1100 |
Measure cable run |
Blake |
Access Booster (no linac beam) |
1100-1300 |
Measure BTS quadrupole offsets |
Borland |
No beam |
1100-1200 |
Collect SR kicker current waveform data |
Emery |
No beam |
1200-1300 |
SR training with no beam |
Ronzhin/Kimbro |
No beam |
1300-1500 |
SR beam recovery and training |
Ronzhin/Kimbro |
Stored Beam & Injection |
1500-1700 |
Booster requalifications (15-18) |
Fystro |
Stored Beam & Limited Injection |
1500 |
Fill ring with 324 bunches |
Ops |
Stored Beam & Injection |
1500-1800 |
RTFB DAQ card data |
Kallakuri et al |
Stored Beam & Limited Injection |
1700-2200 |
Booster cavity calibration |
Calvey, Berenc |
No Injection |
|
|
|
|
2200-2400 |
PC Gun beam with L2 down |
Dooling |
No Injection |
|
Tuesday, December 14, 2021 |
|
|
0000-0400 |
RG1 PAR injection efficiency |
Yine Sun et al |
No injection |
0400-0600 |
PAR training |
LaBuda/Hotham |
Limited Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |