Machine Studies

Draft Schedule for Run01-4, 2022

February 21st 0800 – February 22nd 0800



Time

Descriptions

Studiers

SR Status


Monday, February 21, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

Replace AC power relay at RF-1

RF Group

No Beam

0930-1130

Test DAC card setup with IOCS40FB

Kallakuri, Brill, Sereno

No Beam

0930-1030

Measure kicker noise and signal levels on the BTS current monitor. No injector beam necessary

Keane

No Beam

1000-1300

Troubleshoot 14ID safety shutter

Klute

Access Zone B ratchet door

1200-1330

PAR training (07-15)

Ronzhin/Hotham

Limited Injection

1330-1400

Re-establish SR beam. Fill 324 bunches.

Ops

Beam and Injection

1400-1500

Interleaving RG2 thermionic gun between PAR and LEA operations

Wootton

Stored Beam & Injection

1500-1600

Check out again LBL BCM in SR for 324 bunches

Emery

Stored Beam & Injection

1500-1800

Booster Injection Optimizer test

Yao Shang

Stored Beam & Injection

1800-2000

Open


Stored Beam & Injection

2000-2400

6 GeV studies

Emery

Stored Beam & Injection


Tuesday, February 22, 2022



0000-0500

Linac data collection

Kuklev

Stored Beam & No Injection

0500-0700

Open


Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection